The plaintiff, Otomic Contractors Ltd., sought partial indemnity costs after successfully claiming damages and upholding a construction lien in a four-and-a-half-day trial.
The defendant, Royal 7 Developments Ltd., opposed the plaintiff's claim for $120,902.32, arguing over-preparation and an excessive hourly rate.
The court, applying principles of judicial discretion, reasonableness, and proportionality under the Courts of Justice Act and Rules of Civil Procedure, found the plaintiff's requested hours disproportionately high.
The court awarded the plaintiff $75,000 in fees plus HST and disbursements, totaling $94,724.74 after a credit for a prior costs award.