34 total
Interim disbursements of $40,000 awarded for imminent legal fees to level the playing field.
The applicant wife brought a motion seeking $140,000 in interim disbursements from the respondent husband to cover business valuations, real estate appraisals, and anticipated legal fees.
The court found the requests for valuation and appraisal costs lacked specificity and were premature given the early stage of financial disclosure.
However, the court awarded $40,000 in interim disbursements for imminent legal fees, finding the applicant lacked the means to fund the litigation and the advance was necessary to level the playing field.
Lien claimants' priority for holdback deficiency under s. 78(2) applies once over all building mortgages combined.
Three lien claimants brought a motion in a receivership proceeding to determine the proper interpretation of s. 78(2) of the Construction Act regarding priority over building mortgages.
The claimants argued they were entitled to priority for the holdback deficiency against each building mortgage individually, effectively multiplying their priority amount.
The court dismissed the motion, holding that the lien claimants' priority is limited to the extent of the single deficiency in the owner's holdback over all building mortgages combined, as multiplying the priority would be contrary to the statutory scheme and unfairly prejudice subsequent encumbrancers.
Temporary spousal support granted; income not imputed due to applicant's age and health limitations.
The applicant brought a motion for temporary spousal support following the breakdown of a 14-year relationship.
The respondent argued the applicant was intentionally under-employed and disputed entitlement.
The court found the applicant had a good arguable case for entitlement on non-compensatory grounds, noting her age, health issues, and limited employment prospects.
The court declined to impute income to the applicant and ordered the respondent to pay temporary spousal support of $1,809 per month based on the Spousal Support Advisory Guidelines.
Subcontractor awarded interest and costs on lien claim; contractor's 'pay when paid' defence rejected.
The plaintiff subcontractor brought a motion for summary judgment for interest and costs on its construction lien claim against the defendant contractor.
The principal amount of the lien was agreed upon and paid from security in court.
The defendant argued it was not liable for interest or costs due to an oral 'pay when paid' agreement, as it had not been fully paid by the third-party general contractor.
The court found no evidence of a 'pay when paid' agreement and held the defendant breached the subcontract by failing to pay the plaintiff.
The court awarded the plaintiff pre-judgment interest and costs, and granted the defendant contribution and indemnity for those costs against the third party.
The court awarded indefinite spousal support and equalization but dismissed the wife's tort and trust claims.
Cindy Cordi and Carlo Cordi separated after over three decades of marriage.
Cindy sought divorce, spousal support, equalization of net family property, and damages for alleged abusive behavior.
She also claimed a beneficial interest in a farmhouse owned by Carlo's father, Vincenzo Cordi, or, alternatively, unjust enrichment for contributions made to it.
The court granted divorce, awarded Cindy spousal support at the high end of the Spousal Support Advisory Guidelines range ($3,078 per month indefinitely), and an equalization payment of $5,690.07.
The court imputed income to both parties for support calculations, finding Carlo received undeclared cash and Cindy was intentionally underemployed.
Cindy's claims for damages for intentional infliction of mental suffering, and her claims for a trust or unjust enrichment regarding the farmhouse, were dismissed.
The court expanded a father's interim unsupervised parenting time but adjourned his request for an equal time-sharing schedule, finding it lacked urgency during the COVID-19 pandemic.
The applicant sought urgent relief regarding access to their fifteen-month-old child, Samuel, including unsupervised access and a modified 2-2-3 schedule.
The respondent opposed, arguing the matter was not urgent and brought a cross-motion for continued primary residence and the existing interim access schedule.
The court, applying the "urgency" test from the Chief Justice's Notice to the Profession during the COVID-19 pandemic, found the initial access issue urgent but the request for an equal time-sharing schedule was not.
The court expanded the applicant's interim unsupervised access schedule, emphasizing the child's best interests and the parents' prior co-parenting involvement, while noting the Children's Aid Society found no ongoing violence.
The applicant's request for a 2/2/5 schedule was adjourned for a more fulsome record.
Small Claims appeal allowed; unpaid invoice sufficient evidence of debt where contractor found credible.
The appellant contractor appealed a Small Claims Court decision dismissing its claim for an unpaid final invoice of $14,104.17 for home renovations.
The trial judge had found insufficient evidence to prove the claim because the supporting receipts were not filed, despite finding the contractor credible.
The Divisional Court held this was an error of law, as the invoice itself was sufficient evidence and the respondents failed to lead evidence challenging the specific amounts.
The court substituted its own decision, granting judgment for the appellant in the amount of $13,804.17, deducting only a disputed charge for used heaters.
An unpaid invoice supported by credible testimony is sufficient evidence of debt without attaching underlying receipts.
The appellant contractor appealed the dismissal of its claim for an unpaid final invoice for renovation work.
The Deputy Judge had dismissed both the contractor's claim for payment and the homeowners' counterclaim for deficiencies, finding insufficient evidence for both.
On appeal, the Superior Court found that the Deputy Judge erred in law by requiring supporting receipts for the invoice when the invoice itself, coupled with the appellant's credible testimony and the respondents' admission of receipt, was sufficient evidence.
The court also noted the respondents' failure to properly plead or cross-examine on the invoice's quantum.
The appeal was granted, and judgment was substituted for the appellant, deducting only the cost of disputed heaters.
The respondents' unappealed claim for deficiencies was not reconsidered.
Motion for leave to appeal costs decision dismissed; self-represented litigant must prove lost opportunity costs.
The self-represented appellant sought leave to appeal a costs decision where he was denied costs for his time spent on the litigation.
The trial judge had relied on binding precedent requiring a self-represented lay litigant to demonstrate lost opportunity costs to be awarded costs for their time.
The appellant argued the trial judge failed to exercise discretion under the Rules of Civil Procedure.
The Divisional Court dismissed the motion for leave to appeal, holding that lower courts are bound by principles articulated by higher courts, and the trial judge committed no error in applying the established principle.
A self-represented litigant was denied costs for personal time due to lacking opportunity cost evidence.
The plaintiff, a self-represented litigant who was successful in the main action, sought full indemnity costs from the defendants.
The plaintiff claimed costs for his time expended in litigation, calculated at an hourly rate, plus disbursements and HST.
The defendants opposed, arguing that the plaintiff failed to provide evidence of lost remuneration (opportunity cost) as required for self-represented litigants under *Fong v. Chan* and *Mustang Investigations Inc. v. Ironside*.
The court, bound by these precedents, denied costs for the plaintiff's personal time due to the lack of evidence of opportunity cost, but awarded fixed costs previously ordered by a Master, and allowed most disbursements, disallowing some travel and "Tier 1 Time" claims.
Negligence Case allowed
Dirm 2010 Inc. was substantially successful in a construction lien trial, recovering over $1.3 million.
This decision addresses the issue of costs.
The court, Master C. Albert, fixed costs on a partial indemnity scale, considering factors such as the principle of indemnity, reasonable expectation of the payor, complexity, importance of issues, and proportionality.
Dirm's failure to make a formal settlement offer under Rule 49 resulted in a $6,000 deduction from the awarded costs.
The court also adjusted counsel's hourly rates, reduced the time claimed for a junior lawyer due to excessive docketed time as a student, and disallowed costs for two lawyers attending trial.
Costs were fixed at $354,151.19 payable by Prestressed Systems Incorporated to Dirm 2010 Inc.
Plaintiff awarded proportionate share of settlement funds; claims of oral agreement and trust rejected.
The plaintiff sought a proportionate share of funds deposited into court following the settlement of prior litigation, based on a written 'Acknowledgement' agreement and his financial contributions.
The defendants argued for a prior oral agreement granting priority repayment to their fathers who loaned money for security for costs, and that an express trust was created.
The court found that the 'Acknowledgement' provided for reimbursement based on proportionate monetary contributions, rejecting the defendants' claim of a prior oral agreement for priority repayment to the fathers and finding no express trust.
The plaintiff was awarded 38.37% of the disputed funds, and his claim for exemplary damages was dismissed.
Subcontractor awarded over $1.3 million after general contractor wrongfully terminated concrete topping contract.
Dirm 2010 Inc. brought a construction lien claim against Prestressed Systems Incorporated (PSI) for unpaid work on a concrete topping subcontract for a parking garage.
PSI counterclaimed, alleging Dirm's work was defective and that Dirm fundamentally breached the contract.
The court found that the contract consisted of the negotiated terms, not the onerous unsigned purchase order PSI attempted to impose.
The court held that Dirm's work, while requiring some remediation, did not constitute a fundamental breach.
PSI breached the contract by terminating Dirm without reasonable opportunity to cure and without justification.
Dirm was awarded $1,315,159.20 for completed work, allowable extras, and lost profit, less reasonable backcharges for deficiencies.
The court awarded the successful plaintiff $94,724.74 in partial indemnity costs, reducing the claimed fees to reflect reasonableness and proportionality.
The plaintiff, Otomic Contractors Ltd., sought partial indemnity costs after successfully claiming damages and upholding a construction lien in a four-and-a-half-day trial.
The defendant, Royal 7 Developments Ltd., opposed the plaintiff's claim for $120,902.32, arguing over-preparation and an excessive hourly rate.
The court, applying principles of judicial discretion, reasonableness, and proportionality under the Courts of Justice Act and Rules of Civil Procedure, found the plaintiff's requested hours disproportionately high.
The court awarded the plaintiff $75,000 in fees plus HST and disbursements, totaling $94,724.74 after a credit for a prior costs award.
The court dismissed a motion to remove the respondent's counsel, holding that the evidence sought was privileged and obtainable from other sources.
The Applicant sought to remove the Respondent's counsel, Mr. Salvatore Mannella, from the record, alleging he was a key witness regarding the Respondent's alleged non-disclosure in a previous separation agreement proceeding and had intimate knowledge of family businesses.
The Respondent opposed, arguing privilege, availability of evidence from other sources, and prematurity.
The court dismissed the Applicant's motion, emphasizing the reluctance to interfere with choice of counsel, the privileged nature of the information sought, and the availability of alternative disclosure methods.
The court upheld an excavation contractor's claim for unpaid invoices based on truck counts and dismissed the developer's counterclaim.
Otomic Contractors Ltd. (Otomic), an excavating contractor, sued Royal 7 Developments Ltd. (Royal 7), a property owner and developer, for $217,945.74 in unpaid excavation work on a multi-phased condominium project and sought a construction lien.
Royal 7 counterclaimed for $273,700.31, alleging Otomic failed to complete work and overcharged for volumes, forcing Royal 7 to hire a related company, Toocor Ltd., to finish.
The court found that Otomic's truck count method for billing was reasonable and accepted, and that Royal 7's payments had become slow and holdbacks unpaid, leading to the breakdown.
The court dismissed Royal 7's counterclaim, finding no overcharge and that Otomic was not responsible for Toocor's costs due to the non-arm's length relationship and Royal 7's failure to formally terminate or request Otomic's return.
The court granted Otomic's claim for $217,945.74 and declared its construction lien valid.
Temporary child support ordered based on imputed income; spousal support denied due to financial discrepancies.
The applicant wife brought a motion for temporary child and spousal support, and to sever the divorce from corollary relief issues.
The court noted significant discrepancies and unreasonable spending in both parties' financial disclosures.
The court imputed an income of $54,000 to the respondent husband based on his undisclosed means of funding a monthly deficit.
The court ordered temporary child support based on the imputed income, denied temporary spousal support at this time, and granted the severance of the divorce on consent.
Appeal from confirmation of Master's report dismissed; findings of fixed price contract and privity upheld.
The appellant appealed an order dismissing its motion to oppose the confirmation of a Master's report.
The Master had found the appellant liable for the balance of an unpaid account for garage roof repairs under a fixed price contract.
The Divisional Court dismissed the appeal, finding that the Master's conclusions regarding the existence of a fixed price contract and privity of contract were supported by the evidence and contained no palpable and overriding error.
Successful party awarded reduced costs after temporary spousal support motion.
Following a long motion concerning temporary and retroactive spousal support, the court determined costs.
The primary issue in the underlying motion involved imputing income to both parties and relied on competing expert reports from income valuators.
Although the applicant was successful in obtaining a temporary spousal support order, neither party’s offer to settle closely matched the outcome.
Applying Rules 18 and 24 of the Family Law Rules and considering factors such as complexity, counsel rates, time spent, and reasonableness of behaviour, the court reduced the applicant’s claimed costs.
Costs were fixed at $15,000 plus HST and limited disbursements, while the substantial expert report expense was deferred to trial for determination.
Motion for questioning granted to test contradictory affidavit evidence in a child custody dispute.
The applicant father brought a motion to permit questioning of the respondent mother in a family law proceeding involving custody of their child.
The mother brought a cross-motion for interim custody and other relief.
The court reviewed the divergent case law on whether questioning should be permitted under Family Law Rule 20(5).
Finding that questioning is a valuable tool to test contradictory affidavit evidence and narrow issues, the court granted the motion, allowing each party to question the other for up to two hours, subject to specific subject matter limitations.
The court also granted parts of the mother's cross-motion on consent, including orders for child care expenses and financial disclosure, and adjourned the balance of her motion.