The plaintiffs sued a contractor and its principal for breach of a contract to construct a turn-key restaurant in a leased strip-mall space.
The court found the defendants agreed to complete the project by a specified deadline, failed to meet that deadline and two later written guarantees, and were responsible for multiple construction and equipment deficiencies, including electrical work, ventilation, fixtures, seating, and sprinkler upgrades.
The court rejected the claim for lost business profits as unsupported, but enforced a weekly liquidated damages clause and awarded thrown-away operating expenses for the pre-addendum delay period.
On the counterclaim, the defendants were permitted only to set off the contractual $10,000 holdback; all alleged extras were dismissed.
Judgment issued for the plaintiffs for $46,199.10 plus pre-judgment interest.