33 total
Regulators may choose reasonable rate-setting methodology without a mandatory prudence presumption.
The Ontario Energy Board appealed a decision that had required it to apply a mandatory prudence framework when assessing Ontario Power Generation compensation costs in rate-setting.
The majority held tribunal participation in defending its own decision was proper in this regulatory context and found no impermissible bootstrapping on appeal.
The Court held the governing statute did not require a single prudence methodology and permitted the Board to use a mixed approach for costs that were partly committed and partly subject to managerial discretion.
The Board’s disallowance of $145 million in compensation costs was found reasonable, and its original decision was reinstated.
TMC had to reflect pro rata electricity costs, not subsidized class-based reallocation.
Applicants under multiple long-term power purchase agreements sought declarations that the respondent miscalculated Total Market Cost after the 2011 global adjustment reallocation regime came into force.
The court held that the contractual definition of TMC implicitly required aggregated electricity costs to be allocated pro rata based on electricity consumption, and that the respondent's new formula improperly reflected a regulatory reallocation between customer classes rather than the underlying costs of generation and supply.
Although the court found the respondent breached the PPAs, it also held that neither the change of law clauses nor the material change provisions were triggered by the reallocation regulation.
Declaratory and consequential relief was granted requiring recalculation from January 1, 2011 and compensation with interest.
Injunction to enforce employment non‑compete refused for lack of strong prima facie case.
An employer sought an interlocutory injunction enforcing a non‑competition covenant against a former executive who joined a competitor.
The employer alleged breach of a 2008 employment agreement and argued that, where a clear negative covenant is breached, the usual injunction test should not apply.
The court applied a modified RJR‑MacDonald test and held the employer failed to establish a strong prima facie case because the covenant may have been superseded by a later agreement and was arguably overly broad and unnecessary to protect legitimate interests.
The court also noted that the inevitable disclosure doctrine is not recognized in Canada and that evidence of irreparable harm was speculative.
The motion to enjoin the employee and the competitor was dismissed, although the employee was ordered not to disclose confidential information or solicit the employer’s customers.
Committed labour costs required prudence review, not hindsight benchmarking.
The appellants challenged a regulatory decision reducing a power generator's proposed revenue requirements for nuclear compensation costs during a forward test period.
The Court of Appeal held that future compensation costs mandated by existing collective agreements were committed costs, not forecast costs that could simply be managed downward.
The Board acted unreasonably by relying on hindsight and current benchmarking information unavailable when the collective agreements were made, and by failing to conduct a prudence review based on what was known or ought to have been known at the time of the commitments.
The matter was remitted to the Board for rehearing in accordance with those principles.
Appeal dismissed; utility cannot recover rate deferral amounts without a prudency review by the Board.
The appellant electricity distributor appealed a Divisional Court decision upholding the Ontario Energy Board's refusal to allow recovery of $14.9 million from a rate deferral account.
The appellant argued that a 2002 interim order had approved its revenue requirement and rate deferral plan, and that subsequent legislation (Bill 210) had deemed the interim order final.
The Court of Appeal dismissed the appeal, finding it reasonable for the Board to conclude that the interim order did not approve the revenue requirement or deferral plan, as no prudency review had occurred.
The Court noted the appellant could still apply to the Board for a proper prudency review.
OEB has jurisdiction to require an electricity distributor to obtain independent director approval for dividends.
The Ontario Energy Board (OEB) imposed a condition on Toronto Hydro-Electric System Limited (THESL) requiring approval from a majority of its independent directors before declaring future dividends to its affiliates, due to concerns over large dividend payouts amidst aging infrastructure.
The Divisional Court struck down this condition, finding the OEB exceeded its jurisdiction.
The OEB appealed.
The Court of Appeal allowed the appeal, holding that the OEB's broad rate-setting powers under the Ontario Energy Board Act included the jurisdiction to impose such a condition to protect ratepayers.
The Court found the OEB's decision was reasonable and did not improperly usurp corporate law principles, as it merely added a regulatory check to the directors' discretion.
Appeal dismissed; OEB reasonably denied recovery of deferred electricity distribution costs absent a prudency review.
The appellant, a licensed electricity distributor, appealed a decision of the Ontario Energy Board denying the recovery of approximately $15 million in deferred costs accumulated in a regulatory asset account.
The appellant argued that a 2002 interim rate order implicitly approved the deferral plan and that subsequent legislation freezing rates made the order final, entitling them to recovery.
The Divisional Court dismissed the appeal, finding the Board's decision reasonable.
The Court held that the interim order did not approve the deferral plan and that the Board was justified in requiring a prudency review before allowing the recovery of costs from ratepayers.
Leave to appeal interlocutory injunction in family commercial lease dispute dismissed.
The plaintiffs sought leave to appeal an interlocutory injunction granted in favour of the defendants in a dispute between two family-owned companies over commercial lease rent payments.
The plaintiffs argued the motions judge erred in finding irreparable harm and exceeded his jurisdiction by characterizing their conduct as illegal.
The Divisional Court dismissed the motion for leave to appeal, finding no reason to doubt the correctness of the motions judge's decision and concluding the matter did not raise issues of public importance justifying a hearing by a full panel.
OEB lacks jurisdiction to require independent director approval for utility dividend declarations.
Toronto Hydro-Electric System Ltd. appealed a decision of the Ontario Energy Board that required any dividend paid by the utility to its parent company be approved by a majority of its independent directors.
The Divisional Court allowed the appeal, finding that the Board lacked both express and implied jurisdiction under the Ontario Energy Board Act, 1998 to impose restrictions on the corporate process for declaring dividends.
The condition was found to be an unwarranted intrusion into corporate governance and contrary to established corporate law principles.
Motion to intervene by first wife in second wife's family law appeal dismissed for undue delay and prejudice.
The moving party, the first wife of the respondent husband, sought leave to intervene in an appeal regarding a vesting order made in favour of the husband's second wife.
The trial judge had ordered the husband's beneficial interest in certain corporate properties vested in the second wife to satisfy substantial support arrears.
The moving party, who also held foreign judgments for support arrears against the husband, sought to intervene to protect her interests.
The Court of Appeal dismissed the motion, finding that the intervention was instigated by the husband to frustrate the second wife's recovery, and that allowing it at this late stage would unduly delay and prejudice the second wife's rights.
Appeal dismissed; OEB's decision to deny recovery of regulatory and interest costs was reasonable.
The appellant gas distributor sought to recover unrecorded gas costs, regulatory costs, and interest charges resulting from an accounting error.
The Ontario Energy Board allowed the recovery of the unrecorded costs deferred over three years but denied the recovery of regulatory costs and interest charges.
The Court of Appeal determined the applicable standard of review was reasonableness and upheld the Board's decision, finding it was open to the Board to balance the utility's right to recover prudently incurred costs against the impact on consumers caused by the utility's own accounting error.
Tribunal order set aside for failing to include tenant renovation costs in the calculation of rent.
The landlords appealed an order of the Tribunal regarding the calculation of rent.
The Divisional Court found that the Tribunal erred in law by failing to attribute the cost of renovations made by the tenants to the amount of rent payable, as defined in the Tenant Protection Act.
Despite the lack of a transcript due to an inaudible recording, the Court allowed the appeal, set aside the Tribunal's order, and fixed the legal monthly rent at $3,000, requiring the tenants to pay arrears.
Appeal dismissed; Energy Board reasonably balanced utility and customer interests in denying interest on late-reported costs.
The appellant, a natural gas distributor, appealed a decision of the Ontario Energy Board that denied the recovery of interest and regulatory costs associated with $531,794 in prudently incurred but late-reported gas costs.
The Board had allowed the recovery of the principal amount over three years to mitigate the impact on customers.
The Divisional Court dismissed the appeal, finding that the Board's decision involved policy considerations and rate-setting expertise, was subject to a reasonableness standard of review, and was a reasonable balancing of utility and customer interests.