35 total
Drainage Act appeals dismissed; Tribunal upheld Engineer's Report finding costs commensurate with benefit and no benefit to neighbouring lands.
The appellants appealed a decision of the Court of Revision confirming an Engineer's Report regarding the Ronson Municipal Drain.
The appellants conceded that the drainage works were required but argued that the benefit derived was not commensurate with the cost, and that neighbouring properties should have been assessed for a benefit because surface water flowed from those properties onto the appellants' land.
The Tribunal dismissed the appeals, finding that the construction and engineering costs were reasonable and commensurate with the benefit.
The Tribunal preferred the evidence of the respondent's experts, who concluded that only the appellants' property would benefit from the drainage works, over the appellants' expert, who had not conducted independent investigations and lacked experience with the Drainage Act.
A resident's application challenging municipal decisions and council conduct was summarily dismissed for lack of standing.
The decision addresses an application by Warren Michael Cummings seeking various forms of relief against the Mayor, Councillors, Chief Administrative Officer, and the Corporation of the County of Norfolk.
The court considered requests for review of a Municipal Election Compliance Audit Committee decision, the conduct of council in passing a by-law, the appointment of an auditor or investigator, and the right of residents to challenge legal bills.
The court found that Mr. Cummings lacked standing for the relief sought, that the requests were frivolous, and summarily dismissed the application under Rule 2.1.01 of the Rules of Civil Procedure.
Court exercises discretion to award compound prejudgment interest at prime rate to fully compensate plaintiff.
Following a trial where the defendants were found liable in nuisance and negligence for flooding the plaintiff's lands, the parties disagreed on the calculation of prejudgment interest (PJI).
The plaintiff sought PJI based on the Canadian bank prime rate compounded annually, while the defendant argued for the statutory rate under s. 128 of the Courts of Justice Act.
The court exercised its discretion under s. 130 of the Act to award compound interest at the prime rate, finding that the statutory rate would under-compensate the plaintiff and provide an unwarranted financial windfall to the defendants who had avoided maintenance costs for decades.
City and neighbouring industrial owner found liable in nuisance, negligence, and strict liability for reoccurring flooding.
The plaintiff, National Steel Car Limited, brought an action against the City of Hamilton, ArcelorMittal Dofasco Inc., and the Hamilton Port Authority for damages caused by reoccurring flooding to its property from the Kenilworth Avenue Drainage Channel.
The court found the City and AMD liable in nuisance, negligence, and strict liability under the rule in Rylands v. Fletcher for failing to maintain the channel and altering its flow, which caused substantial and unreasonable interference with the plaintiff's property.
The action against the Hamilton Port Authority was dismissed.
The court awarded the plaintiff over $5.2 million in compensatory damages, granted a permanent mandatory injunction requiring the City and AMD to remediate and maintain the channel, and awarded punitive damages of $500,000 against AMD and $400,000 against the City.
Tribunal approves Procedural Order and Issues List for railway company's appeal of residential development approval.
The Ontario Land Tribunal held a Case Management Conference regarding an appeal by the Canadian National Railway Company against the City of Hamilton's approval of an Official Plan Amendment and Zoning By-law Amendment.
The amendments would permit a 447-unit residential development near a railway yard.
The Tribunal received an update on mediation efforts and approved the draft Procedural Order and Issues List to govern the upcoming nine-day merits hearing scheduled for May 2024.
Tribunal schedules third Case Management Conference and nine-day merits hearing pending ongoing mediation.
The Ontario Land Tribunal held a second Case Management Conference regarding an appeal by the Canadian National Railway Company against the City of Hamilton's approval of an Official Plan Amendment and Zoning By-law Amendment for a 447-unit residential development.
The parties agreed to continue with Tribunal-led mediation.
The Tribunal scheduled a third Case Management Conference for December 19, 2023, to finalize the Procedural Order and Issues List, and a nine-day hearing of the merits commencing on May 21, 2024.
Party status granted and second Case Management Conference scheduled in residential development appeal.
The Tribunal held a first Case Management Conference regarding an appeal by the Canadian National Railway Company against the City of Hamilton's approval of an Official Plan Amendment and Zoning By-law Amendment for a 447-unit residential development.
The Tribunal granted party status to City Housing Hamilton Corporation on consent.
A second Case Management Conference was scheduled to finalize the Procedural Order and Issues List, and the parties indicated they were exploring Tribunal-led mediation.
The court ordered the unsuccessful party in estate litigation to personally pay fixed costs.
This endorsement addresses costs for two motions: John James's motion to remove Lory James as Estate Trustee and appoint an Estate Trustee During Litigation (ETDL), and Lory James and Glacier Trading Corporation's motion to strike John's counterclaim.
The court previously granted the appointment of an ETDL and dismissed the motion to strike the counterclaim.
The court determined that costs should be fixed immediately rather than reserved for trial, emphasizing the "loser pays" principle in estate litigation.
John James was deemed the overall successful party on his motion, and entirely successful on the motion to strike.
The court awarded John James $10,000 in costs against Lory James personally for his motion, and $5,500 jointly and severally against Lory James and Glacier Trading Corporation for their unsuccessful motion to strike.
Summary judgment granted dismissing negligent misrepresentation claim against environmental consultant due to third-party disclaimer clause.
The plaintiff purchased property from the defendant church to build social housing.
Prior to the sale, the church retained the defendant environmental consultant to conduct a Phase I Environmental Site Assessment.
The consultant's report, which contained a standard disclaimer clause limiting liability to third parties, was provided to the plaintiff by the church without the consultant's knowledge or consent.
After closing, the plaintiff discovered soil contamination and sued the church and the consultant for negligent misrepresentation.
The consultant moved for summary judgment.
The court granted the motion, finding that the disclaimer clause effectively excluded any duty of care owed to the plaintiff, and dismissed the action and crossclaims against the consultant.
On-site wood storage and grinding to heat greenhouses is a permitted accessory use.
A homeowner appealed a lower court decision that upheld a greenhouse operator's use of storing and grinding wood on-site as an accessory use under the local zoning bylaw.
The homeowner sought a declaration that the wood storage and grinding operations violated the zoning bylaw.
The Court of Appeal upheld the lower court's decision, finding that storing and grinding wood for heating greenhouses constitutes a natural and normal incident of operating a greenhouse and therefore qualifies as an accessory use under the bylaw definition.
The court rejected the homeowner's argument that a restrictive interpretation of "naturally and normally incidental" was required.
Appeal dismissed; contractor's claims against insurer and adjuster for unpaid work properly dismissed on summary judgment.
The appellant contractor appealed a summary judgment dismissing its claims against an insurer and an independent adjuster for unpaid repair work following a fire.
The appellant argued the motion judge erred in finding no contract existed with the insurer or adjuster, and in dismissing its unjust enrichment claims.
The Divisional Court dismissed the appeal, finding no palpable and overriding error in the motion judge's conclusion that the written contract was solely with the property owner and that the insurer and adjuster received no real benefit from the work.
Leave to appeal the substantial indemnity costs order was also denied.
Successful responding parties awarded $33,000 in partial indemnity costs despite applicant's lower own costs.
Following the dismissal of the applicant's application to direct the registration of a tax deed, the successful responding parties sought partial indemnity costs.
The applicant argued that the costs awarded should be limited to the amount of its own legal costs in bringing the application, relying on the principle that the unsuccessful party's costs can indicate the parties' expectations.
The court rejected this argument, noting that the application posed a significant financial risk to the responding parties, justifying their higher costs.
The court fixed costs at $22,000 for the municipality and $11,000 for the mortgagee.
Judicial review Application dismissed
The applicant, 2494044 Ontario Inc., sought an order directing Norfolk County to register a tax deed for a commercial property after being the highest tenderer in a tax sale.
The County cancelled the tax sale after the previous mortgagee paid the outstanding taxes.
The court found that the County Treasurer acted reasonably in exercising discretion under section 382(6)(a) of the Municipal Act to cancel the tax sale, as it was not in the municipality's financial interest to continue.
The application was dismissed, affirming the Treasurer's decision.
Appeal dismissed; spouse of registered landowner lacks standing as an 'owner' under the Drainage Act.
The appellant appealed a decision of the Acting Drainage Referee denying him standing under the Drainage Act to appeal a drainage works report.
The appellant argued he had standing as the spouse of the registered owner of the affected property and as a resident who paid bills.
The Divisional Court upheld the Referee's decision, finding it reasonable that the Family Law Act did not confer an ownership interest for the purposes of the Drainage Act, and that residing in the home did not make the appellant an 'owner'.
The court also dismissed arguments related to the Protection of Public Participation Act and a request for a stay, ultimately dismissing the appeal and awarding costs to the respondents.
Summary judgment was granted to enforce a commercial mortgage and dismiss a professional negligence counterclaim.
Hamilton Cab Company Inc. and John Dean sought summary judgment against Jaspal Gill and related numbered companies concerning outstanding debt, mortgage enforcement, and a counterclaim for professional negligence.
The court granted Hamilton Cab's motion for possession of mortgaged properties and partial summary judgment for $470,487.62, with additional debt to be determined on a reference.
The court dismissed the Gill defendants' counterclaim against John Dean, finding no genuine issue for trial regarding the validity of the agreements or the solicitor's standard of care.
The Court of Appeal upheld a summary judgment dismissing the appellant's corporate claims due to lack of standing as a majority shareholder.
The appellant appealed a summary judgment decision dismissing her claims against the respondents.
The central issue was whether the appellant was the sole or majority shareholder of John Bordynuik Inc. of Delaware and therefore entitled to bring claims on behalf of or as an assignee of that company.
The motion judge found that the respondent John Bordynuik was not obliged to give up his shares in the Delaware Company when he purchased his majority interest in JBI Inc. of Nevada.
The Court of Appeal upheld the motion judge's findings, accepting her interpretation of the documentary evidence, including an email and share ledger, over the appellant's interpretation of a Settlement Agreement.
The appeal was dismissed with costs fixed at $25,000 inclusive of disbursements and applicable taxes.
Application to exempt tree removal from municipal forest conservation by-law as a normal farm practice dismissed.
The applicants sought a determination under the Farming and Food Production Protection Act that their removal of trees to straighten a field line was a normal farm practice, exempting them from the municipality's Forest Conservation By-Law.
The Board found that the applicants failed to prove the tree removal was a normal farm practice, noting the clearing exceeded what was necessary to straighten the field and amounted to an attempt to clear cut a portion of the bush.
The application was dismissed.
Appeal of Drainage Referee's interlocutory orders dismissed for lack of standing and jurisdiction.
The appellant sought to appeal several interlocutory orders made by an Acting Referee under the Drainage Act, including an order dismissing a recusal motion.
The Divisional Court dismissed the appeal on multiple grounds.
First, the appellant lacked standing as he was not the registered owner of the property.
Second, the orders appealed from were interlocutory and therefore final and not subject to appeal under section 106(3) of the Drainage Act.
Finally, the court found no unfairness in the Acting Referee hearing his own recusal motion, as this accords with usual practice.
The court awarded the successful applicants $60,237.93 in partial indemnity costs following an injunction against a police firing range.
The applicants sought substantial indemnity costs or, alternatively, partial indemnity costs after successfully obtaining an injunction to shut down a police firing range.
The respondent had offered to cease activity without costs, which the applicants rejected due to wanting costs and environmental clean-up.
The court dismissed the claim for substantial indemnity costs, finding no reprehensible conduct by the respondent.
However, the court found the applicants' partial indemnity claim of $60,237.93 to be reasonable given the complexity and importance of the case, and ordered the respondent to pay this amount.
The court permanently enjoined a police firing range due to unlawful intensification and zoning non-compliance.
The applicants sought declarations and an injunction against Norfolk County regarding a police firing range on county land.
The court found that the firing range was not lawfully established before August 5, 1986, and thus was not a permitted or legal non-conforming use under subsequent bylaws.
Furthermore, even if it had been initially lawful, its significant intensification over the years, including expanded hours, increased lanes, and stray bullets on adjacent property, constituted a "difference in kind" in its community impact, thereby losing any potential acquired rights.
The court dismissed the respondent's defence of laches, finding the community's delayed complaints reasonable given the initial limited use and subsequent dramatic intensification and safety concerns.
An order was issued declaring the facility unlawful and granting a permanent injunction.