The appellant appealed municipal enforcement actions arising from construction of a structure without a building permit, including an order to comply and a subsequent stop work order issued under the Building Code Act.
The initial order to comply and related prosecution were withdrawn, but a later stop work order and new charges under municipal bylaws, the Planning Act, and the Provincial Offences Act remained.
The appellant sought broader relief including injunctions preventing further enforcement actions and a stay or transfer of provincial offences proceedings.
The court treated the matter as an appeal of the stop work order and rescinded that order due to procedural irregularities leading to its issuance.
However, the court declined to grant injunctions or interfere with ongoing provincial offences prosecutions, holding that those proceedings were the proper forum to determine whether the structure had been unlawfully erected.