The applicants were wholly successful in their application for mandatory orders requiring the demolition of structures built without building permits, and in dismissing the respondents' counter-application.
The court determined costs by written submissions.
The respondents argued the costs sought were excessive and that the applicants had over-lawyered the matter.
The court rejected these arguments, finding the time spent and rates charged by the applicants' senior counsel to be fair, reasonable, and proportional.
The court awarded the applicants their requested partial indemnity costs of $25,643.68, inclusive of fees, disbursements, and HST.