The applicant appealed the failure of the Town of Caledon to adopt an Official Plan Amendment, and the refusal by the Niagara Escarpment Commission of development permits, to allow a new aggregate extraction operation (gravel pit).
Prior to the hearing, the applicant reached a settlement with the Town, the Commission, and a neighbouring property owner, resulting in revised site plans and conditions that addressed concerns regarding water, natural heritage, noise, and air quality.
The Tribunal accepted uncontested expert planning evidence that the revised proposal represents good land use planning and meets all legislative tests.
The appeals were allowed in part on an interim basis, contingent upon the Crown advising that adequate Indigenous consultation has occurred.