The defendants jointly applied for a stay of proceedings under s. 11(b) of the Charter due to unreasonable delay.
The total delay was 618 days, exceeding the 18-month Jordan ceiling.
The Crown argued for a reduction in delay due to defence actions and inactions.
The court found that a joint prosecution was justified and that the defence acted as a collective.
Specific periods of delay were attributed to the defence, including 44 days due to one counsel's unavailability for a JPT, 11 days due to a change in counsel, and 95.5 days due to the collective defence's delay in raising s. 11(b) concerns and not utilizing backlog initiatives.
Alternatively, one defendant was found solely responsible for 306 days of delay due to counsel's unavailability for an earlier trial date, which was then communally shared.
In both scenarios, the net delay fell below the Jordan ceiling.
The court also found that the defence failed to demonstrate meaningful steps to expedite proceedings or that the case took markedly longer than it should have.
The application for a stay of proceedings was dismissed.