Unlock 3 more sections of this judge’s background. Start your 7-day free trial.
Appeared as counsel in 17 cases (2011–2018)
The court validated email service and consolidated two related actions concerning a share purchase agreement.
The plaintiffs, John Snow and Sherry Snow, brought motions to consolidate two related actions and to validate service of the statement of claim and motion materials on the defendants.
The court granted both motions, finding that service by email should be validated given the defendants' actual notice of the claim, and that consolidation was appropriate as both actions arose from the same share purchase agreement and related promissory note.
The court also set a timetable for the consolidated action and addressed the process for amending pleadings and exchanging costs submissions.
The court set aside a noting in default and dismissed a motion for default judgment due to inconsistent evidence regarding the alleged loan agreement.
The plaintiff, Shamsul Alam MD, moved for default judgment against the defendant, Azam Khan a.k.a.
MD Azam Khan, regarding alleged loans for construction at eight properties.
The defendant sought to set aside the noting in default.
The court found the evidentiary record insufficient to grant default judgment and noted inconsistencies in the plaintiff’s affidavits and the nature of the parties’ relationship.
Despite the defendant’s significant delay and lack of explanation, the court set aside the noting in default to allow the matter to proceed on the merits, emphasizing the need for a fair trial and the complexity of the issues.
The court dismissed the defendant's motion for security for costs and a prohibition order due to delay and lack of jurisdiction.
The court dismissed the defendant Universal Protection Service of Canada Corporation’s motion for security for costs and a prohibition order against the plaintiff, Qun Zheng.
The court found that the motion for security for costs was not warranted at this late stage of the proceeding, given the delay in bringing the motion and the relatively small amount of unpaid costs from other proceedings.
The court also held that it lacked jurisdiction to prohibit Mr. Zheng from taking further steps in the action or from appealing without leave, as such orders would be overbroad and not supported by the Rules of Civil Procedure or the Courts of Justice Act.
The court denied the plaintiff's request to extend deadlines for an out-of-time discovery motion.
The plaintiff sought an extension of the set down deadline and directions on scheduling a motion to compel the defendant to produce additional documents, arguing these were required by a prior production order.
The court found the plaintiff's motion was out of time, as the parties had agreed to a timetable for all pre-trial motions, and the plaintiff had not acted within those deadlines.
The court emphasized the importance of case management and procedural fairness, but held that the plaintiff had ample opportunity to bring the motion and declined to grant leave for it to proceed.
The court upheld a material supplier's construction lien and contract claim while dismissing a subcontractor's untimely lien but granting its contract claim.
This trial resolved two outstanding subcontractor and supplier construction lien actions arising from a condominium development project.
The supplier, Senso, sought payment for building materials, while the subcontractor, TMAP, sought payment for door and trim installation work from the contractor, DC&F, and the owner, Finch.
The court found that Senso's lien was timely and valid, allowing it to recover its lien amount from security posted in court, and granted Senso a contract judgment against DC&F. Although TMAP's contract claim against DC&F was successful, the court dismissed TMAP's lien claim because it failed to prove that it supplied lienable services within the statutory period.
Additionally, the court rejected DC&F's 'pay-when-paid' defense and determined that Finch's statutory holdback obligations exceeded Senso's proven lien.
The court settled an order following a judge's retirement by strictly adhering to the original written reasons rather than the parties' subsequent agreement.
The court was asked to settle the wording of a formal order after the associate judge who made the underlying discovery ruling had retired.
The dispute arose because the parties’ previously agreed draft order did not match the wording of the original reasons, and the registrar refused to sign it.
The court held that in settling the order, it could not revisit the merits, infer a different intention, or implement the parties’ own understanding of what had been meant; it had to ensure the order tracked the reasons as written.
The court therefore signed the plaintiff’s revised draft order with some clarifying amendments and made no order as to costs of the settling process.
The successful defendant in a construction lien action was awarded substantial indemnity costs after the plaintiffs rejected multiple settlement offers.
This costs endorsement follows the dismissal of two construction lien actions brought by JCL Concrete Pumping Limited and Ontario Trucking and Disposal Ltd. against SEMA Railway Structures Inc. and Metrolinx.
The court addresses the parties’ submissions on costs, ultimately awarding substantial indemnity costs to SEMA, the successful party, and rejecting the plaintiffs’ arguments for limiting or reducing costs.
The decision reviews the applicable statutory framework, the conduct of the parties, and the offers to settle, and finds that SEMA’s costs were reasonable and proportionate in the circumstances.
An ex parte motion to declare a construction lien expired was dismissed due to insufficient evidence and the moving party's improper prior unilateral deletion of the lien.
Starbank Developments 285 Corp. brought an ex parte motion to declare the plaintiff’s construction lien expired and to vacate the certificate of action from title.
The court found that Starbank had not met the high evidentiary onus required for such a motion, citing insufficient and improper evidence, and concerns about the unilateral deletion of the lien from title without notice to the lien claimant.
The motion was dismissed without prejudice, with directions that any further motion must be brought on notice to the plaintiff and in Brampton, except for a vacating motion under s. 44(1) of the Construction Act.
The court dismissed a motion for security for costs due to the defendants' unexplained delay and the arguable merits of the plaintiff's claims.
The court dismissed the defendants’ motion for security for costs against Icon Wheelchairs Canada, finding that the delay in bringing the motion and the arguable merits of the plaintiff’s claims made such an order unjust.
The court also fixed costs for the discontinued action by Icon Wheelchairs Inc., but stayed payment pending the outcome of the defendants’ counterclaim.
The decision provides a detailed analysis of the legal framework for security for costs, the impact of delay, and the assessment of the merits of the underlying claims.
The court permitted a non-party spouse to attend continued examinations for discovery by videoconference to assist counsel, balancing fairness and preventing disruption.
The court considered a motion by Joanne Fox to permit her spouse, Evan Kirsh, to attend continued examinations for discovery in a Construction Act action, for the purpose of assisting her counsel.
The plaintiff, Irwin Allen Design Build Inc. (IADB), opposed further attendance by Mr. Kirsh, citing alleged disruptive behaviour and negative impacts on its deponent.
The court exercised its discretion to allow Mr. Kirsh’s attendance, subject to conditions: he may attend the examination of Mr. Allen only by videoconference and may attend Ms. Fox’s examination in person or by videoconference, but must not interfere or act as a witness.
The decision balances fairness to both parties, considering Mr. Kirsh’s prior attendance, his role as a material witness, and the need to avoid disruption.
The court ordered an interim pro rata distribution of admitted basic holdback to validated lien claimants while retaining funds for disputed liens.
This decision concerns the interim distribution of the admitted basic holdback under the Construction Act in a complex construction lien reference.
The court fixes the minimum basic holdback obligation of 35 Mercer Limited and orders pro rata payment to certain validated lien claimants, while holding the balance pending further determination of disputed liens, particularly that of 1086289 Ontario Inc. o/a Urban Electrical Contractors.
The ruling addresses the allocation of holdback among multiple classes of lien claimants and the treatment of disputed and unproven liens.
A participant expert's evidence was partially struck where opinions on construction deficiencies were based on hearsay rather than personal observation.
This decision concerns a mid-trial motion in a construction lien action.
The plaintiff, Village Homes Inc., sought to strike portions of the affidavit and report of the defendant’s witness, Yu Ching Lai, regarding the presence of rebar and concrete in a disputed wall and observations of wall cracking.
The court found that Mr. Lai lacked personal knowledge regarding the rebar and concrete, as his evidence was based on hearsay from a video, and struck those portions.
However, the court allowed Mr. Lai to testify about his personal observations of wall cracking.
The ruling also addresses the parties’ discovery and production obligations, the scope of undertakings, and the admissibility of participant expert evidence.
Contractor awarded unpaid balance but construction lien declared expired due to work abandonment.
This decision concerns a construction lien action arising from a condominium project at 200 Woodbine Avenue, Toronto.
Elembe (LMB) Mechanical Ltd. claimed for unpaid contract work and extras, while Two Hundred Inc. counterclaimed for overpayment and deficiencies.
The court found that LMB had partially proved its claim for extras and was entitled to an earned and unpaid contract balance, but failed to prove that any amounts were due and payable as of the date it suspended work.
The court also found that LMB breached the contract by suspending and abandoning work, resulting in the expiry of its lien rights.
Two Hundred Inc. failed to prove its counterclaim for deficiencies.
Judgment was granted to LMB for the unpaid contract balance, but its lien was declared expired.
The court struck a proposed expert's litigation reports for non-compliance with rule 53.03 but permitted him to testify as a participant expert.
The court ruled on the admissibility of expert evidence in a construction lien action.
The defendant sought to call Michael Colalillo, a structural engineer, as an expert under rule 53.03 of the Rules of Civil Procedure.
The court found that Mr. Colalillo did not meet the requirements to testify as a rule 53.03 expert due to non-compliance with the rule’s requirements for expert reports.
However, the court permitted Mr. Colalillo to testify as a participant expert, subject to a qualification voir dire, as his opinions were based on his personal observations and participation in the project.
The court struck his litigation reports and affidavit sworn February 11, 2025, but allowed his earlier affidavit and appended reports from 2022 to be admitted.
The court dismissed the defendant's eve-of-trial adjournment motion, finding insufficient medical evidence to support the principal's inability to participate.
The court denied the defendant’s motion to adjourn a peremptory trial week in a Construction Act lien action, finding insufficient medical evidence to support the principal’s inability to participate.
The decision reviews the discretionary nature of adjournment requests, the need for transparency and timely disclosure, and the importance of summary proceedings in lien actions.
The court found no compelling grounds for adjournment and highlighted the risk of prejudice and delay to the plaintiff and the administration of justice.
The court dismissed a motion to discharge a construction lien, finding triable issues regarding the parties' relationship and lien quantification.
The court considered a motion by the defendants to discharge the plaintiff’s construction lien and dismiss the action as frivolous, vexatious, or an abuse of process, or for delay.
The dispute centered on whether the plaintiff was a proper lien claimant, the nature of his relationship with the defendants (partnership or subcontractor), and whether the lien was properly quantified.
The court found triable issues on the relationship and quantification, dismissed the motion to discharge the lien, and imposed a timetable for the next steps in the litigation.
Defendant was granted leave to call late-served witnesses but ordered to pay costs.
The decision addresses whether the defendant, Valerie Connelly, should be granted leave to call five disputed witnesses at trial in a construction lien action, despite failing to comply with a court-ordered deadline for serving trial evidence.
The court finds that while Ms. Connelly failed to adequately explain her breach, the interests of justice favour allowing her to call four of the five witnesses, with the breach compensable in costs.
The court also sets a revised timetable for trial steps, addresses costs thrown away, and fixes costs of the hearing, emphasizing the importance of compliance with court orders and balancing procedural fairness.
Motion for a charging order dismissed as the client was not unwilling to pay fees.
This motion concerned an application by Capo Sgro LLP, former lawyers for the plaintiff Haven Property Services Corp., for a charging order over settlement proceeds to secure unpaid legal fees and disbursements.
Haven opposed the motion, arguing that Capo Sgro LLP was not instrumental in achieving the settlement and that Haven was able and willing to pay its fees, subject to a pending assessment under the Solicitors Act.
The court found that while Capo Sgro LLP's efforts were instrumental in the settlement, there was insufficient evidence to demonstrate that Haven was unable or unwilling to pay its outstanding legal fees.
The court emphasized that non-payment alone or commencing a fee assessment does not constitute unwillingness to pay.
The motion for a charging order was dismissed, and Haven was awarded costs.
A subcontractor's recovery against property owners is limited to the statutory holdback amount under the Construction Act.
This lien action concerned a substantial home renovation project.
The plaintiff, Hannan Custom Building Ltd., claimed for unpaid services and materials.
The defendants, the Owners, denied a direct contract with the plaintiff, asserting their contract was with DC Builders Ltd., and that Hannan Building was a subcontractor.
The court found no direct contract between the plaintiff and the Owners, but rather a contract between the Owners and DC Builders, making the plaintiff a subcontractor.
The plaintiff's claim against the Owners was thus limited to the basic holdback amount under the Construction Act, subject to proven set-offs for deficiencies.
The court granted judgment to the plaintiff for the basic holdback amount.
The court granted in part a motion for a further affidavit of documents, ordering production of specific records while dismissing speculative requests.
The plaintiffs brought a motion seeking to strike the statement of defence or compel a further and better affidavit of documents from the defendant, the Town of Oakville, in a construction dispute.
The motion to strike was not pursued.
The court granted the motion for a further affidavit of documents in part, finding the Town's initial affidavit deficient and ordering a supplementary affidavit with specific relevant documents, including those related to privilege claims.
However, many of the plaintiffs' broad production requests were dismissed due to insufficient evidence of relevance or existence, with the court emphasizing that such inquiries are better suited for examination for discovery.
The court also rejected the Town's threshold objections regarding unpaid costs and failure to agree on a discovery plan, noting that the latter default was shared by both parties.