Siemens Canada Limited brought a motion for summary judgment seeking to limit its liability to Symtech Innovations Ltd. to admitted holdback and to dismiss Symtech's significant prolongation claim.
The court found that Symtech failed to provide timely contractual notice of its prolongation claim, which was a condition precedent to maintaining the claim.
Consequently, the prolongation claim was dismissed.
However, the court found genuine issues requiring a trial regarding Siemens' alleged breaches of the sub-subcontract and the quantification of other earned and unpaid amounts.
The court also declined to grant summary judgment in a related breach of trust action, noting jurisdictional differences.