44 total
The court dismissed a subcontractor's claim for costs thrown away, finding its intended legal position lacked merit and awarding costs to the responding parties.
This costs endorsement addresses competing costs claims arising from a motion regarding holdback allocation and distribution in a construction lien reference.
Flocor Inc. sought costs thrown away against the Urban Parties (Urban Integrated Group Inc., Urban Mechanical Contracting Ltd., and Standard Fire Protection Inc.) claiming they misrepresented the contractual relationship between the defendants.
The Urban Parties sought costs against Flocor for unnecessary expense incurred in responding to Flocor's evidence and costs claim.
The court rejected Flocor's claim for costs thrown away, finding that Flocor had ample notice of the correct contractual relationships and that its intended legal position lacked sufficient merit.
The court awarded costs to the Urban Parties for the costs submissions phase only.
Lien security posted for one claim cannot be fully returned upon settlement without considering prejudice to other pooled lien claimants.
The defendant 35 Mercer Limited brought a motion to reduce the construction lien of the plaintiff Urban Electrical Contractors (UEC) by $4,333,708.96.
Prior to the hearing, Mercer, UEC, and Urban Integrated Group Inc. (UIG) settled the motion on terms reducing UEC's lien security by $3,231,464.75.
Subsequently, Mercer and UEC reached a separate settlement to fully discharge UEC's lien and return all security.
However, UIG opposed the full return of security because UIG's own liens had been vacated with reduced security that accounted for UEC's lien security already posted.
The court held that security for one lien cannot be returned without considering other lien claimants affected by that return, and ordered reduction only to the extent of UIG's consent.
The court also declined to award costs, finding the parties had settled the motion without judicial intervention on the merits.
Motion for leave to appeal dismissed with costs fixed at $6,000.
The moving parties sought leave to appeal a decision of the Superior Court of Justice.
The Divisional Court dismissed the motion for leave to appeal and awarded costs to the responding parties in the fixed amount of $6,000.
Debtor denied leave to appeal receivership Approval and Vesting Order under the Bankruptcy and Insolvency Act.
The court-appointed receiver brought a motion seeking a declaration that the debtor had no automatic right of appeal from an Approval and Vesting Order under the Bankruptcy and Insolvency Act, and an order denying leave to appeal.
The debtor argued it had an automatic right of appeal under s. 193(a) or (c) of the BIA, or alternatively sought leave under s. 193(e).
The Court of Appeal held that the debtor had no automatic right of appeal, as the order did not affect future rights or result in a direct loss exceeding $10,000.
The Court also denied leave to appeal, finding the proposed appeal lacked merit, did not raise an issue of general importance, and would unduly hinder the insolvency proceedings.
A registered mortgage advanced without written notice of unregistered construction liens has priority over those liens beyond the statutory holdback.
The applicants, a first mortgagee, sought a declaration that the priority of construction lien claims against unsold condominium units was limited to the statutory holdback amount, and authorization for the receiver to distribute net sale proceeds to the mortgagee.
Two lien claimants opposed, arguing for full priority based on alleged fraudulent conveyance and the nature of the mortgage advance.
The court found that the Construction Act's priority regime is a complete code, and since the lien claims were not preserved or perfected, nor was written notice provided to the mortgagee before the advance, the mortgage had priority over the liens beyond the statutory holdback.
The court also rejected arguments of fraudulent conveyance and the claim that the funds were not a proper "advance in respect of the mortgage." The motion was granted, allowing the receiver to distribute proceeds to the mortgagee while maintaining a holdback reserve for valid lien claims.
The Construction Lien Act applies because the procurement process commenced before July 1, 2018.
This motion, part of a larger reference concerning the Nobu Residences condominium complex, addressed the application of the transition provisions in section 87.3 of the Construction Act.
The core issue was whether the former Construction Lien Act (CLA) or the current Construction Act applied to the improvement and associated liens, which directly impacted lien timeliness.
The owner, 35 Mercer Limited, the contractor, Urban Integrated Group Inc., and a lien claimant, Brunco Insulation Ltd., argued for the application of the CLA, while Desco Plumbing and Heating Supply Inc. contended the current Construction Act should apply.
The court found that the CLA continues to apply to the improvement and all liens arising from it, based on evidence that a procurement process for the improvement commenced before July 1, 2018.
The court rejected arguments that the owner's affidavit was deficient, that ex parte vacating orders were binding, that the onus to provide transition dates was "murky" or that project delays like the COVID-19 pandemic should influence the application of section 87.3.
Summary judgment denied; genuine issues for trial exist regarding inconsistent election and unjust enrichment.
The moving party, Unity Health, sought summary judgment to dismiss four actions brought by subcontractor plaintiffs, arguing that the plaintiffs' settlement with the surety (Zurich) constituted an inconsistent election that precluded their alternative claims against Unity Health.
Unity Health also sought to dismiss the plaintiffs' unjust enrichment claims and, alternatively, to stay two of the actions for failure to immediately disclose the settlement.
The court dismissed the motions, finding genuine issues for trial regarding the doctrine of inconsistent election and the unjust enrichment claims.
The court also held that the settlement was disclosed in a timely manner once it was finalized, so a stay was not warranted.
A subcontractor's construction lien was vacated because it failed to prove its last date of supply.
This construction lien reference involved a summary trial of an issue concerning the timeliness and bona fide nature of Honeywell Limited's claim for lien against Bondfield Construction Company Limited.
The Lien Vetting Committee, comprising Ozz Electric Inc., Urban Mechanical Contracting Ltd., and Zurich Insurance Company Ltd., argued that Honeywell's lien had expired.
The court found that Honeywell failed to prove its claimed last date of supply, as the evidence provided was deficient and contradictory.
The court also addressed the application of the rule in Browne v. Dunn, concluding it was not engaged because the contradictions were within the witness's own affidavit.
Furthermore, the court commented that even if the last date of supply had been proven, the supply after receiving notice of Bondfield's financial issues would not have been bona fide.
Consequently, Honeywell's lien was ruled to have expired and was ordered vacated.
The Court of Appeal affirmed that the presence of innocent third parties is not an absolute bar to rescinding a surety bond induced by fraud.
The appellants, a group of subcontractors and a bank, appealed an application judge's decision that rescission of surety bonds might be possible even if it affects innocent third parties.
The bonds were issued by Zurich Insurance Company Ltd. for a large construction project, but Zurich later discovered alleged fraudulent misrepresentations and collusion that induced it to issue the bonds.
The appellants sought a declaration that rescission was unavailable as a matter of law due to the involvement of innocent third parties.
The Court of Appeal dismissed the appeal, affirming that prejudice to third parties is not an absolute bar to rescission, especially in cases of fraudulent misrepresentation, and that such a determination requires a full factual record at trial.
Action stayed in favour of arbitration as dispute arguably fell within scope of settlement agreement.
The defendants brought a motion to stay the plaintiffs' oppression and breach of fiduciary duty action in favour of arbitration under s. 7 of the Arbitration Act, 1991.
The parties, who are siblings, had previously settled an arbitration but reserved rights regarding the sale of certain properties.
The court applied the Haas framework and found there was an arguable basis that the arbitral panel had jurisdiction over the dispute.
The action was stayed pending the outcome of the arbitration, with costs awarded to the defendants.
Surety granted leave to intervene in construction lien reference due to direct interest in holdback distribution.
Zurich, the surety for the insolvent general contractor Bondfield, brought a motion to intervene as a party in a construction lien reference.
Zurich sought to participate in a vetting committee for the distribution of the owner's holdback among the timely lien claimants.
The court granted the motion, finding that Zurich had a direct interest in the holdback because it had made significant holdback advances to the major electrical and mechanical trades and had taken partial assignments of their lien rights.
The court ordered the timely claimants to pay Zurich's costs of $30,000.
Self-represented plaintiff's motion to amend pleadings dismissed as frivolous, scandalous, and an abuse of process.
The self-represented plaintiff brought a motion to amend her Statement of Claim, add new party defendants, compel further documentary production, and compel additional examinations for discovery in her wrongful dismissal action.
The court found the proposed 85-page amended pleading to be replete with evidence, irrelevant arguments, and inflammatory attacks, violating the rules of pleading.
The motion was dismissed in its entirety as frivolous, scandalous, vexatious, and an abuse of process.
The parties were ordered to proceed to mediation and then examinations for discovery.
Defendant's counterclaim struck for non-compliance with orders, but final opportunity granted to defend plaintiff's claim.
The plaintiff moved to strike the self-represented defendant's statement of defence and counterclaim due to his failure to comply with court orders, including failing to serve affidavit evidence-in-chief and refusing to answer discovery questions.
The court struck the defendant's set-off defence and counterclaim, finding he had failed to pursue them meaningfully.
However, the court declined to strike the statement of defence entirely, granting the defendant one final peremptory deadline to serve his trial evidence to allow him to defend the plaintiff's claim on its merits.
The court struck negligence and unjust enrichment claims as an abuse of process.
The defendant, Broccolini Construction (Toronto) Inc., brought a motion to strike various paragraphs of the Fresh as Amended Statement of Claim filed by Urban Mechanical Contracting Ltd. The motion was based on the argument that the impugned paragraphs constituted an abuse of process by attempting to relitigate issues previously determined by Sossin J. The court reviewed Sossin J.'s prior decision, which had limited Urban's claims to those within a specific "Delay Claim" carved out of a settlement agreement, excluding tort and unjust enrichment claims against Broccolini.
The motion to strike was partially granted, with specific references to negligence and unjust enrichment claims being struck without leave to amend, as they were found to be an abuse of process.
The court awarded the plaintiff $5,000 in costs for a discovery motion due to the defendants' elusive conduct.
This is a costs endorsement following motions to compel discovery answers.
The Plaintiff, Vanalt Electrical Construction, Inc. (VEC), sought costs for its motion, while the Defendants, Ozz Electric Inc. et al., sought costs or reservation.
The court awarded VEC $5,000 in partial indemnity costs, finding that the Defendants' conduct unnecessarily prolonged the discovery process and increased litigation expenses.
Costs related to 33 adjourned questions were reserved for future determination.
The court awarded the successful defendant $585,000 in costs, applying a substantial indemnity scale for trial due to the plaintiff's reprehensible pursuit of unsubstantiated punitive damages.
The plaintiff's action against the defendants was dismissed.
This endorsement addresses the costs payable by the plaintiff, Ms. Liddy, to the defendant, Ms. Mauro.
Ms. Mauro sought substantial indemnity costs of over $650,000, or partial indemnity then substantial indemnity costs of over $613,000, based on Ms. Liddy's unreasonable conduct, rejection of settlement offers, and pursuit of unsubstantiated allegations, including punitive damages.
Ms. Liddy argued for partial indemnity costs at no more than 50% of Ms. Mauro's fees, blaming the City of Vaughan defendants for delays and a mistrial.
The court found Ms. Mauro's offers reasonable and Ms. Liddy's conduct, particularly the persistent punitive damages claim without evidentiary support, reprehensible.
The court awarded Ms. Mauro $585,000 in costs, inclusive of disbursements and taxes, assessed on a partial indemnity scale until the start of trial and on a substantial indemnity basis thereafter.
Nuisance and negligence claims dismissed as plaintiff's own landscaping caused the property drainage issues.
The plaintiff brought an action in negligence, nuisance, and trespass against her neighbours and the City of Vaughan, alleging that construction activities on the neighbours' property altered the grading and caused water to flow onto her property, resulting in damages.
The claims against the municipal defendants were settled during trial.
The court dismissed the remaining claims against the neighbour, finding that the plaintiff failed to prove causation.
Expert evidence established that the water problems were actually caused by the plaintiff's own landscapers, who had flattened the common swale and altered the grading on her property, preventing proper drainage.
The court found no negligence or unreasonable interference by the neighbour.
Portions of statement of claim struck as an abuse of process for violating prior settlement release.
The defendants brought a motion under Rules 21 and 25 to strike portions of the plaintiff's statement of claim in a construction dispute.
The parties had previously executed minutes of settlement that released all claims except for a specific delay claim.
The court found that the plaintiff's claims extending beyond the delay claim were barred by the settlement release and struck them as an abuse of process.
The court also limited documentary discovery primarily to the period after the performance date.
Parties ordered to produce specific documents related to set-off and credits in construction discovery motions.
The plaintiff and defendants brought cross-motions to compel answers to undertakings, under advisements, and refusals arising from examinations for discovery in a construction dispute.
The plaintiff sought information regarding its trust claims and the defendants' set-off claim, while the defendants sought the plaintiff's pricing and cost documentation for a fixed-price contract.
The Master ordered the defendants to produce a final copy of a change directive and clarify their set-off documentation, adjourning the remaining trust questions.
The Master also ordered the plaintiff to produce documentation supporting a specific credit it had agreed to, finding that the fixed-price nature of the contract did not insulate it from producing documents related to a variation of that price.
The court granted an insolvent construction company CCAA protection and approved a DIP facility to ensure completion of critical public infrastructure projects.
The Bondfield Group, a major construction company, sought CCAA protection due to insolvency, over $1 billion in active contracts, and over 200 lawsuits.
The application was unopposed and resulted from extensive stakeholder negotiations.
The court granted an initial order for CCAA protection, including a stay of proceedings, approval of a tailored $8 million Debtor-in-Possession (DIP) facility funded by Zurich Insurance, an Administration Charge for professional fees, and a Directors' Charge for $3 million (excluding John Aquino).
The court emphasized the public interest in completing critical infrastructure projects and the preference for CCAA over receivership to preserve enterprise value.