19 total
Judicial review dismissed; Ministry fulfilled its duty to consult First Nations before transferring Crown land.
The applicant First Nations sought judicial review of the Ministry's decisions to amend a Crown Land Use Policy Atlas and transfer a parcel of Crown land to the Municipality of Red Lake for housing development.
The applicants argued the Ministry breached its duty to consult under s. 35 of the Constitution Act, 1982, and failed to obtain their consent.
The Divisional Court dismissed the application, finding that Treaty No. 3 allows the Crown to take up land subject to a duty to consult, which does not amount to a First Nation veto.
The court held that the duty to consult was at the lower end of the spectrum and that the Ministry's consultation process was reasonable and fulfilled its constitutional obligations.
Appeals allowed for Official Plan and Zoning By-law amendments and consents to permit a wellness retreat centre.
The applicants appealed the Municipality of Shuniah's refusal of an Official Plan Amendment and Zoning By-law Amendment, and its failure to make a decision on Consent applications, to permit the creation of two new lots and the development of a wellness retreat centre.
The Tribunal allowed the appeals, finding that the proposed development has regard for provincial interests, is consistent with the Provincial Policy Statement, and conforms to the Growth Plan for Northern Ontario and the municipal Official Plan.
The Tribunal was satisfied that the proposed use is compatible with the surrounding rural and shoreline residential area and that environmental features would be appropriately protected through a 30-metre buffer.
Party status granted to 19 neighbouring property owners on consent at first Case Management Conference.
The Ontario Land Tribunal held a first Case Management Conference regarding appeals by Alan and Tamara Hutchinson against the Municipality of Shuniah's refusal of applications for an Official Plan Amendment, Zoning By-Law Amendment, and consents to permit a wellness retreat centre.
The Tribunal granted party status to 19 neighbouring property owners on consent.
A five-day merit hearing was scheduled to commence on July 8, 2024, by video hearing.
Drainage Act appeal dismissed; proposed municipal drain alignment upheld as technically sound and necessary.
The appellant appealed a municipal engineer's report proposing a new drainage works under section 48 of the Drainage Act, arguing that the drain should be constructed on an alternative alignment or as a mutual agreement drain.
The appellant claimed the proposed works would negatively impact his property and proposed agricultural development.
The Tribunal dismissed the appeal, accepting the engineer's evidence that the proposed alignment was hydraulically efficient, necessary to alleviate surface ponding, and that the appellant's alternative was significantly more expensive and technically inferior.
The Tribunal affirmed the municipality's right to proceed via petition rather than mutual agreement.
Appeal of summary judgment dismissal in wrongful dismissal action denied due to genuine issues for trial.
The appellant employer appealed an order dismissing its motion for summary judgment in a wrongful dismissal action.
The employee had been terminated for cause following two off-duty assaults.
The Divisional Court upheld the motions judge's finding that genuine issues for trial existed, including whether the employer had prior knowledge of one assault, whether the employee's developmental disability was known and accommodated, and whether mitigating factors were properly considered.
The appeal was dismissed.
Successful plaintiff on summary judgment motion awarded $15,000 in costs.
Following the plaintiff's success on the defendant's motion for summary judgment and venue change in a wrongful dismissal action, the parties made written submissions on costs.
The plaintiff sought partial indemnity costs of $18,129.55, while the defendant proposed $12,000.
Applying the overriding principle of reasonableness, the court fixed the plaintiff's costs at $15,000 inclusive of HST and disbursements.
The court granted an injunction against unauthorized property maintenance but refused one against unproven defamation.
The appellants sought relief to stop the respondent from harassing and defaming the mayor, town council members, and staff through abusive emails and statements.
The application judge refused to grant any relief sought, including a declaration that the respondent's conduct breached the Town's harassment policies and a permanent injunction against defamatory statements.
On appeal, the court upheld the refusal to issue a broad injunction against defamatory speech absent a prior finding of defamation, but allowed the appeal in part by granting an injunction restraining the respondent from maintaining or purporting to maintain any town property without permission.
The court awarded costs to the appellants.
The employer's motions for summary judgment and venue transfer in a wrongful dismissal action were dismissed.
The defendant brought a motion for summary judgment to dismiss the plaintiff's wrongful dismissal and Human Rights Code claims, and alternatively, a motion to transfer the proceeding from Thunder Bay to Kenora.
The court dismissed the summary judgment motion, finding genuine issues requiring a trial, particularly regarding the defendant's knowledge of the plaintiff's developmental limitations and the fairness of the termination investigation.
The court also dismissed the venue transfer motion, affirming the plaintiff's prima facie right to choose venue and finding the defendant did not demonstrate Kenora was significantly better than Thunder Bay.
Court has jurisdiction under Courts of Justice Act to grant relief from deemed forfeiture of tax sale surplus.
The appellant's property was sold in a municipal tax sale, resulting in a surplus of over $76,000 which was paid into court.
The appellant missed the one-year statutory deadline to apply for payment out of court by three weeks, resulting in a deemed forfeiture of the funds to the municipality under s. 380(6) of the Municipal Act, 2001.
The application judge held he lacked jurisdiction to grant relief from forfeiture.
The Court of Appeal allowed the appeal, holding that s. 98 of the Courts of Justice Act provides jurisdiction to grant relief from the deemed forfeiture, as the statutory scheme does not expressly or implicitly preclude it.
The court granted relief from forfeiture and ordered the surplus paid to the appellant.
Appeal of counterclaim dismissal for delay denied; appellant failed to comply with status hearing timetable.
The appellant appealed the dismissal of his counterclaim for delay.
He had failed to deliver an affidavit of documents or prepare a discovery plan as required by a consent timetable order issued at a status hearing.
The appellant argued the motion judge should have applied Rule 24, which places the onus on the moving party to show inordinate and inexcusable delay.
The Court of Appeal upheld the motion judge's decision, finding no error in requiring the appellant to explain his delay under rule 48.14 and noting the court's power to dismiss a proceeding for failure to comply with an interlocutory order under rule 60.12.
Appeal dismissed; claim for 2003 repair costs stemming from 1986 sewer deficiency is statute-barred.
The appellant appealed a decision finding its claim for recovery of repair costs for a deficient sewer system was statute-barred.
The Court of Appeal agreed that the essence of the claim was a breach of duty in 1986 requiring repairs in 2003, and found no basis to interfere with the lower court's decision.
The appeal was dismissed with costs awarded to the respondent.
Motion to amend pleadings denied and action dismissed as proposed negligence claims were statute-barred.
The defendant municipality brought a motion for summary judgment to dismiss the plaintiff's action regarding sewer system issues.
The plaintiff conceded its existing claims but sought to amend its statement of claim to add causes of action in negligence and negligent misrepresentation.
The court found that the plaintiff discovered the alleged negligence by late 2003 when it began constructing its own sewage lift station.
The court rejected the plaintiff's argument that the negligence was a continuing cause of action.
As the limitation period had expired, the proposed amendments were statute-barred, constituting non-compensable prejudice.
The motion to amend was denied and the action was dismissed.
Costs of $93,000 awarded to the successful appellant municipality, payable primarily by Ontario.
The appellant municipality was successful on appeal and sought costs for the proceedings before the application judge and the Court of Appeal.
The Court of Appeal awarded costs to the appellant on a party and party basis.
Ontario was ordered to pay the costs of the application ($50,000), factum motion ($2,000), and appeal ($35,000).
Lac Seul First Nation and Northern Nishnawbe Education Council were ordered to pay the costs of the stay motion ($6,000).
No costs were awarded for or against Canada.
Municipality not responsible for maintaining provincial roads where statutory transfer mechanisms were not utilized.
The appellant municipality appealed a declaration that it was responsible for maintaining two roads leading to a First Nation reserve and an education centre following a municipal restructuring order.
The application judge had found the roads became municipal highways through statutory dedication under the Municipal Act and common law dedication by conduct.
The Court of Appeal allowed the appeal, holding that the Municipal Act provisions relied upon explicitly excluded provincial roads under Crown control.
Furthermore, the common law doctrine of dedication and acceptance could not apply because the public already enjoyed a statutory right of passage under the Public Lands Act, and the province had failed to use the available statutory mechanisms to transfer the roads.
Creditor had standing to bring s. 38 bankruptcy action as no binding settlement with estate existed.
The appellants appealed an order dismissing their motion to set aside an order granted under s. 38(1) of the Bankruptcy and Insolvency Act, which authorized a creditor to pursue a fraudulent conveyance action in the trustee's stead.
The appellants argued the creditor lacked standing because it had settled its claims against the bankrupt.
The Court of Appeal held that the appellants had standing to challenge the s. 38 order due to allegations of abuse of process.
However, the Court found the creditor was a valid creditor at the date of bankruptcy and no binding settlement had been concluded with the bankrupt estate.
The appeal was allowed in part only to set aside a costs provision and stay the trustee's original motion, but otherwise dismissed.
Lease renewal clause upheld; duration of term was reasonably certain and municipal proprietary powers applied.
The appellant tenant sought to renew a cottage lease with the respondent municipality.
The municipality argued the renewal clause was void for uncertainty regarding the duration of the term, and that it lacked the power to enter the renewal without Ontario Municipal Board approval.
The application judge found the renewal clause void for uncertainty.
The Court of Appeal reversed, holding that the duration of the renewal term could be ascertained from the lease's express terms.
The Court also held that the municipality was exercising its proprietary powers, not divesting legislative powers, and that OMB approval was not required because no costs were to be raised in a subsequent year.
Appeal allowed; claim for rectification of a restrictive covenant should not have been struck out.
The appellant sold a surplus grain terminal to a purchaser with an agreement intended to include a restrictive covenant preventing the property's use for grain handling.
The property was later sold in a tax sale to a new purchaser who intended to use it for grain handling.
The appellant sued for a declaration that the restrictive covenant ran with the land and sought rectification of the original agreement if the covenant was found defective.
The motion judge struck out the rectification claim as disclosing no reasonable cause of action and declared the covenant did not survive the tax sale.
The Court of Appeal allowed the appeal, finding that it was not plain and obvious that the rectification claim could not succeed, and set aside the declaratory orders.
Quantum of costs payable by the Commission to the City fixed at $47,907.91.
The adjudicator determined the quantum of costs payable by the Ontario Human Rights Commission to the City of Thunder Bay following a previous order for costs on a party and party basis for 20 hearing days, reduced by 30%.
The City claimed approximately $73,000, while the Commission argued for $18,350.50.
The adjudicator allowed preparation time but excluded the cost of a legal assistant and time spent arguing about costs.
After applying the necessary reductions and pro-rating, the costs were fixed at $47,907.91.
Costs awarded against Human Rights Commission for causing undue hardship by failing to properly investigate complaint.
Following the dismissal of a human rights complaint alleging sex discrimination in municipal hiring, the respondent municipality sought costs against the Ontario Human Rights Commission under s. 41(4) of the Human Rights Code.
The Board of Inquiry found that while the complaint was not trivial, frivolous, vexatious, or made in bad faith, the Commission's failure to properly investigate and assess the merits of the case caused undue hardship to the respondent by unnecessarily prolonging the hearing.
The Board ordered the Commission to pay the respondent's party and party costs for 20 hearing days, reduced by 30 percent because the respondent's own refusal to disclose documents contributed to the delay.