28 total
Interim interim injunction granted to prevent trespass and allow expert access, but denied for landscaping.
The plaintiff moved for urgent injunctive relief against his neighbours, the defendants, alleging their excavation activities encroached on his lands and caused flooding.
The court granted an interim interim injunction enjoining the defendants from trespassing and ordering them to permit the plaintiff's expert access to their property to conduct investigations.
The court declined to enjoin the defendants from conducting further landscaping on their own lands, finding no evidence of irreparable harm.
The Court of Appeal upheld the dismissal of a claim that a road over private property in an unorganized township had become a public highway through dedication and acceptance.
The appellants purchased two parcels of land in an unorganized township in the District of Parry Sound and sought a declaration that Trussler Road, which crossed respondents' private property, was a public highway.
The appellants claimed the road qualified as a public highway under section 261 of the Municipal Act based on colonization road status, statute labour, or dedication and acceptance.
The motion judge dismissed the claims on all grounds.
The Court of Appeal upheld the dismissal, finding no reversible error in the motion judge's conclusion that the appellants failed to establish dedication and acceptance on the evidence.
The court found the use of the road was consistent with neighbourly tolerance rather than public dedication.
Successful plaintiffs in a mortgage and construction dispute were awarded $76,225 in partial indemnity costs.
This decision addresses the issue of costs following a five-day trial concerning defaulted mortgages and construction costs.
The plaintiffs, Barrie Leasing Services Inc. and James Shirley, were found to be the successful parties, having been awarded judgment for outstanding mortgage and construction costs.
The court determined that the plaintiffs were entitled to partial indemnity costs, rejecting their claim for substantial indemnity costs and the defendants' argument that their Rule 49 offer should apply.
The court found that the trial was necessary to resolve live issues, including the distribution of funds held in trust.
The court awarded reduced substantial indemnity costs to mortgagees following a reference on priority of claims, holding the unsuccessful claimants liable for any shortfall.
The court determined costs following a reference decision on priority of claims.
The applicant, Joe Guerrieri, was awarded reduced substantial indemnity costs ($40,000) in priority to all parties except the first mortgagee, Frances Gower.
Gower was awarded significantly reduced substantial indemnity costs ($20,000) with first priority.
Rob Rolston Building Materials Ltd. was awarded $5,000 in costs.
Jerry Schmanda and Dawna Catharine Fairbairn (the Schmandas), whose unsuccessful equitable mortgage claim caused the reference, were made liable for any unrecoverable costs awarded to Guerrieri, Gower, and Rolston.
The court considered Rule 57 factors, proportionality, and settlement offers, noting that while offers were made, none were accepted in a way that avoided the reference hearing costs.
Equitable mortgage and constructive trust imposed on property sale proceeds to repay oral construction loans.
The plaintiffs advanced funds secured by three mortgages on a property owned by the defendant, which went into default.
The plaintiffs also advanced approximately $400,000 in construction costs to build a cottage and boathouse to enhance the property's value for sale.
The property sold for $1,250,000.
The court determined the outstanding mortgage balances and found that while the construction loans were not secured by the third mortgage, there was an implied agreement to pay interest at 5% under the Interest Act.
The court imposed an equitable mortgage and constructive trust over the sale proceeds to secure repayment of the construction costs, finding the defendants were unjustly enriched.
The court invalidated a Notice of Sale issued in breach of a forbearance agreement but declined to release trust funds or stay mortgage enforcement.
The applicants sought an injunction to stay power of sale proceedings, a declaration that a Notice of Sale was invalid, and the release of trust funds to redeem a mortgage.
The respondent opposed, arguing the application should be stayed due to unpaid costs and that the trust funds were subject to a prior court order.
The court declined to stay the application for costs.
It ruled that the trust funds must remain in trust pending the judgment in a separate consolidated action concerning other mortgages.
The court found the respondent's Notice of Sale invalid because it was issued in breach of a forbearance agreement, but clarified that the respondent was free to issue a new, compliant notice.
The request to stay the power of sale proceedings was otherwise dismissed.
Relocation of a shared access road did not substantially impair the applicants' easement rights.
The applicants sought to enforce registered easements over a shared access road (Brewers Close) on the respondents' property, seeking injunctive relief to restore the road to its original condition after the respondents unilaterally relocated a portion of it.
The respondents argued the easements were invalid due to vagueness and, alternatively, that the relocation did not substantially impair the applicants' use.
The court found the easements were not invalid due to vagueness, considering extrinsic evidence, but could not declare them fully valid without tracing their roots.
Crucially, the court determined that the relocation did not substantially impair the applicants' reasonable use of the easement for its granted purpose.
Consequently, both the application and the respondents' counter-application for a declaration of invalidity were dismissed.
The court awarded the successful defendants $36,540 in partial indemnity costs following the dismissal of the plaintiffs' action regarding road access.
This decision addresses the costs arising from the plaintiffs' unsuccessful motion for summary judgment and the dismissal of the balance of their main action concerning the public highway status of Trussler Road.
The defendants, as the wholly successful parties, sought partial indemnity costs.
The court, applying principles from the Courts of Justice Act and Rules of Civil Procedure, awarded the defendants costs for both the motion and the main action, adjusting the hourly rate for counsel to align with previous decisions in the case.
Motion for summary judgment seeking declaration of a public road in an unorganized township dismissed.
The plaintiffs brought a motion for summary judgment seeking a declaration that Trussler Road, located in an unorganized township, is a public road under the Municipal Act, thereby allowing them access to their rural property.
The court found that while the Municipal Act definition of a public highway applies to unorganized townships, the evidence did not establish that Trussler Road was a colonization road, that statute labour was usually performed on it, or that it had been dedicated and accepted for public use.
The court dismissed the plaintiffs' motion for summary judgment and, finding no genuine issue requiring a trial, dismissed the plaintiffs' action in its entirety.
Partial indemnity costs of $20,544.34 awarded to successful plaintiff following summary judgment on defaulted mortgage.
Following a successful motion for summary judgment and possession of land subject to a defaulted mortgage, the plaintiff sought substantial indemnity costs of $32,143.58.
The defendants argued for partial indemnity costs, noting a forbearance agreement was in place and there were live issues regarding the amounts claimed.
The court found the defendants' conduct did not warrant substantial indemnity costs and awarded partial indemnity costs.
Costs were fixed at $20,544.34, inclusive of fees, disbursements, and HST.
The Court of Appeal upheld a decision establishing a property boundary based on a historical fence line rather than surveyor measurements.
The appellants appealed a decision establishing the boundary line between their property and the respondent's property.
The application judge determined that a fence line, rather than a surveyor's measured line, constituted the proper boundary based on surveying principles and historical evidence.
The appellants raised four grounds of appeal, contending the application judge misinterpreted surveyor field notes, failed to properly consider a surveyor's plan, failed to apply proper legal principles, and based the boundary location on facts not in evidence.
The Court of Appeal found no palpable and overriding errors and upheld the lower court decision.
The successful respondent in a property line dispute was awarded costs on a partial and substantial indemnity basis following an unaccepted offer to settle.
This decision addresses costs following a successful cross-application by the respondent, Gordon Robert Anderson, in a land dispute.
The respondent filed costs submissions, while the applicants, Karen Jean Weaver and William Bryce Weaver, did not.
The court applied Rule 49.10(1) of the Rules of Civil Procedure, which entitles a party to partial indemnity costs to the date of an offer to settle and substantial indemnity costs thereafter if they obtain a judgment as favourable as their offer.
Considering factors under Rule 57.01(1), including the complexity of the proceeding, the importance of the issues, and the value of an expert report, the court awarded the respondent $48,654.30 in fees plus applicable taxes, and $17,706.80 in disbursements, to be paid by the applicants within 90 days.
The court resolved a lakefront boundary dispute by prioritizing a historical fence line over subsequent survey measurements.
This case involved a boundary dispute between adjacent property owners on Shawanaga Lake, concerning a piece of land known as "the Point." The applicants sought a declaration of ownership based on a surveyed "White line" while the cross-applicant (respondent) argued the boundary should follow an older fence line, seeking a declaration of ownership or adverse possession.
The court found that the original surveyor erred by not accepting the fence line as the boundary, contrary to established surveying principles and common law.
While acknowledging the historical error, the court ultimately declared the boundary to be the westerly limit of Part 1, Plan 42R-12887, which was consistent with the cross-applicant's long-standing occupation and made the disputed Part 1 his property.
The Land Registry was ordered to amend its records accordingly, and a caution registered by the cross-applicant was vacated.
Summary judgment was granted dismissing the plaintiffs' claim for an access road declaration.
The defendants brought a motion for partial summary judgment to dismiss the plaintiffs' claim for a declaration that their property access was an "access road" or "common road" under the Road Access Act.
The plaintiffs cross-moved for summary judgment, asserting the access was a public highway or, alternatively, an access/common road.
The court applied summary judgment principles, finding no genuine issue requiring a trial regarding the "spur road" not meeting the Act's definitions.
Evidence indicated the spur road had not been used by motor vehicles for over 30 years, was overgrown, and lacked a railway crossing mechanism, thus not serving as a motor vehicle access route.
The defendants' motion was granted, dismissing the plaintiffs' claim under the Act.
The plaintiffs' cross-motion regarding the public highway claim was adjourned, and the alternative claim regarding access/common road was dismissed.
Appeal dismissed; motion judge had jurisdiction to grant summary judgment to non-moving party.
The appellant Town appealed a summary judgment order granted in favour of the respondent commercial tenant.
The Town had evicted the tenant for rent arrears and later sold a router left on the premises, applying the funds to charity.
The Town brought a motion for summary judgment arguing the limitation period had expired, but the motion judge granted summary judgment in favour of the tenant.
The Court of Appeal dismissed the appeal, finding the motion judge had the power to grant judgment for the non-moving party and correctly held the limitation period began when the tenant learned of the sale.
Lease interpreted as two‑year term but terminated for tenants’ non‑payment of rent.
A dispute arose from a homemade commercial farm lease containing inconsistent provisions regarding the lease term.
The tenants sought declarations regarding the lease term, access to the property, and injunctions relating to interference with their farming operations, while the landlords counter‑applied for a declaration that the lease had ended or was properly terminated for cause.
The court applied principles of contractual interpretation, including the dominant purpose of the agreement and consideration of surrounding circumstances, to resolve ambiguity between a clause stating a two‑year term and another describing the lease as a “one year lease.” The court concluded that the lease term ran from December 1, 2011 to November 1, 2013.
However, the tenants’ deliberate non‑payment of rent for several months constituted a breach entitling the landlords to terminate the lease, and the tenants were ordered to pay arrears and vacate the premises within a defined period.
Tribunal findings on structural defect created issue estoppel; liability determined on summary judgment.
Homeowners brought motions to amend their statement of defence and counterclaim to particularize defective installation of a radiant in‑floor heating system and to obtain summary judgment based on findings from the Licence Appeal Tribunal under the Ontario New Home Warranties Act.
The court held the amendment was not a new cause of action but merely a particularization of negligence already pleaded concerning the concrete foundation and construction defects.
Applying issue estoppel principles, the court found the Tribunal’s determination that the heating system constituted a major structural defect was a final judicial decision between the same parties and resolved the same issue.
Summary judgment was therefore granted on liability for breach of contract relating to the heating system, but damages were left for determination at trial.
Successful party awarded $6,000 in costs after resisting family law motion.
Following a family law motion in which the moving party sought leave to add a third party, conduct questioning, and amend the application to advance constructive and equitable trust claims, the court addressed the issue of costs.
The responding party was generally successful in resisting the motion.
The court found no factors warranting elevated or substantial indemnity costs.
Costs were therefore fixed on a standard basis.
The moving party was ordered to pay a lump sum costs award to the successful party.
Motion to add respondent's spouse and amend pleadings for constructive trust dismissed due to lack of property link and limitation period.
The applicant sought leave to add the respondent's wife as a party, to question her, and to amend her application to include a constructive trust claim.
The applicant and respondent had a long personal relationship and children together, while the respondent maintained a double life, remaining married to his wife.
The court dismissed the motion to add the wife as a party, finding no direct link between the applicant's contributions and the wife's property, and noting it would unnecessarily complicate the litigation.
The motion to amend the claim was also dismissed, as the proposed constructive trust claim appeared to be statute-barred under the Limitations Act, 2002, though the applicant was permitted to explore tracing of funds during the respondent's questioning.
Historic trail declared public highway by implied dedication; barriers ordered removed.
The plaintiffs sought declarations that a trail crossing several private properties constituted a public highway, or alternatively an access road protected under the Road Access Act.
The court examined historical evidence, municipal expenditures on maintenance, and longstanding public use to determine the legal status of the roadway.
It held that the road became a public highway through implied dedication and municipal acceptance, applying the principle of “once a highway, always a highway.” The court rejected the plaintiffs’ claim that the road had a 66‑foot width and instead determined the historical roadway width was 1.4 metres.
Barriers placed by neighbouring landowners preventing passage were ordered removed.