The Plaintiff, AZZ Galvanizing Canada Limited, brought a motion to compel discovery responses from the Defendants, Empire Steel Inc. and 1340614 Ontario Inc. (IBT).
The motion primarily concerned the disclosure of hydro cost allocation and subtenant information (Issue 14) by Empire.
While the initial motion was broad, issues were narrowed by agreement, and IBT's portion was adjourned due to counsel's unavailability.
The court found in favour of the Plaintiff on Issue 14, compelling Empire to provide the requested information.
This endorsement addresses the costs of that motion.
The court awarded partial indemnity costs of $16,094.69 to the Plaintiff, finding them largely successful.
The court rejected Empire's arguments for costs against the Plaintiff, citing improper submissions and the lack of novelty in the legal issues.
The costs were deemed fair, reasonable, and proportionate given the complexity and importance of the issues.