13 total
Director ordered to present evidence first at merits hearing for environmental compliance approval appeal.
At a Case Management Conference regarding an appeal of conditions imposed on an Amended Environmental Compliance Approval for a decommissioned uranium mine, the parties finalized a draft Procedural Order and Issues List.
The parties disputed the order of evidence for the upcoming merits hearing.
The Tribunal ordered that the Director of the Ministry of the Environment, Conservation and Parks present evidence first, finding it necessary to explain the regulatory framework and rationale for the appealed conditions.
Appeal dismissed; second action for continuing environmental contamination barred as abuse of process following earlier dismissal for delay.
The appellant railway company appealed a partial summary judgment dismissing its claims for ongoing coal tar contamination as an abuse of process.
The appellant had previously commenced an action in 1989 for historical and continuing coal tar migration, which was dismissed for inordinate delay and failure to preserve evidence.
The appellant commenced a new action in 2014 claiming damages for continuing migration since 2012.
The Court of Appeal dismissed the appeal, holding that the continuing tort claims were exhausted by the dismissal of the 1989 action, and allowing the 2014 action to proceed would undermine finality and bring the administration of justice into disrepute.
Case management conference adjourned to facilitate settlement discussions regarding environmental compliance approval conditions.
The Tribunal convened a Case Management Conference regarding an appeal by Denison Mines Inc. of conditions attached to an Amended Environmental Compliance Approval for the decommissioning of a former uranium mine.
The parties jointly requested an adjournment to facilitate settlement discussions.
The Tribunal granted the adjournment and scheduled a further Case Management Conference.
Consent motion to stay environmental compliance approval condition granted subject to alternative monitoring requirements.
The appellant brought a motion for a stay of Condition 5.4 of an Amended Environmental Compliance Approval regarding the decommissioning of a former uranium mine.
The parties reached a proposed resolution to stay the condition, subject to alternative monitoring and reporting requirements.
The Tribunal found that the statutory tests for a stay under the Environmental Protection Act were met, as the proposed stay would not hinder monitoring, cause danger to human health, or impair the environment.
The Tribunal granted the stay on consent and scheduled a Case Management Conference.
The court granted partial summary judgment dismissing historical coal tar contamination claims as an abuse of process but allowed newer benzene contamination claims to proceed.
The court granted summary judgment dismissing Canadian National Railway Company's claims relating to coal tar contamination as an abuse of process, since those claims had already been dismissed in 2014 due to inordinate delay and failure to preserve evidence.
The court found that the same fairness concerns that prevented a fair trial in 2014 persisted.
However, the court allowed CN's claims regarding benzene contamination to proceed, finding that these claims did not crystallize until 2014 and were not part of the earlier action.
The decision clarifies the application of res judicata and abuse of process in the context of environmental contamination and continuing torts.
Further Case Management Conference scheduled to allow parties to continue settlement discussions regarding Environmental Compliance Approval.
The Ontario Land Tribunal held a Case Management Conference regarding an appeal by the appellant against an amendment to an Environmental Compliance Approval.
The parties reported progress in settlement discussions and requested a further conference.
The Tribunal scheduled a further Case Management Conference and permitted participants to make written submissions prior to the conclusion of settlement discussions.
Adjournment granted to allow ongoing review of environmental compliance approval applications; participant status granted.
The appellant appealed an amendment to an Environmental Compliance Approval for its quarry.
At a pre-hearing conference, the parties requested a three-month adjournment to allow the Ministry to review concurrent applications for the quarry and a neighbouring grinding facility.
The Tribunal granted the adjournment and scheduled a continuation of the pre-hearing conference.
The Tribunal also granted Participant status to two individuals who had previously been granted Presenter status under the former Environmental Review Tribunal rules.
Leave granted for post-set-down motion to inspect and sample non-party property for environmental contamination.
The plaintiffs brought a motion for an order to permit them to obtain soil and groundwater samples from a neighbouring property owned by a non-party, after the action had been set down for trial.
The plaintiffs sought the samples to allow their expert to perform forensic environmental testing to respond to the defendants' expert reports regarding PCB contamination.
The court granted leave to bring the motion, finding the expert's need for additional sampling constituted an unexpected change in circumstances.
The court also granted the inspection order, concluding that the testing would be useful and probative in determining whether the contaminants on the plaintiffs' property originated from the neighbouring property.
Tribunal approves settlement amending environmental penalty orders and dismissing appeals upon payment of $80,151.40.
Lafarge Canada Limited appealed three Environmental Penalty Orders issued by the Director of the Ministry of the Environment, Conservation and Parks regarding alleged exceedances of total suspended solids and reporting failures at its quarry and cement terminal.
The parties reached a settlement agreement wherein the Director agreed to amend the orders to remove certain contraventions and associated penalties, as the discharges did not meet the definition of 'process effluent'.
Lafarge agreed to pay the remaining penalty amounts totaling $80,151.40.
The Environmental Review Tribunal found the settlement consistent with the Environmental Protection Act and in the public interest, amended the orders, and dismissed the appeals.
Tribunal approves revocation of environmental order where most remediation work was completed and secured.
The Director of the Ministry of the Environment, Conservation and Parks proposed to revoke a 2011 Director's Order against several appellants regarding the decommissioning of a waste disposal site and sewage works at a former paper mill.
The Tribunal found the revocation to be consistent with the Environmental Protection Act and in the public interest, as the majority of the required environmental work had been completed by another party, sufficient financial assurance was held for the remaining work, and one of the appellants had passed away.
The Tribunal directed the revocation of the order and dismissed the proceeding.
The Court of Appeal reversed a summary judgment, finding the motion judge improperly equated suspicion of contamination with actual knowledge for limitation purposes.
The appellant purchased a commercial property that was contaminated by hydrocarbons that had migrated from an adjacent former gas station property.
The respondents moved for summary judgment to dismiss the action as statute-barred under the Limitations Act, 2002, arguing that the appellant knew or ought to have known of the contamination more than two years before commencing the action.
The motion judge granted the motion, finding that the appellant had knowledge of the claim by March 9, 2012, or alternatively by March 30, 2012.
The Court of Appeal allowed the appeal, finding that the motion judge made palpable and overriding errors by equating the appellant's suspicion of contamination with actual knowledge of contamination, and by failing to consider the relevant circumstances of the multi-property transaction and the waiver of conditions.
The initial contamination claim was dismissed as statute-barred, but continuing nuisance proceeds to trial.
The defendant, Imperial Oil Ltd., moved for summary judgment to dismiss the plaintiff's (Valco Instruments Canada Corporation) action for damages in negligence and nuisance due to petroleum hydrocarbon (PHC) migration.
Imperial Oil argued the claim was statute-barred by the Limitations Act, having been discovered in 2001 or 2006, and that there was no genuine issue for trial regarding continuing nuisance.
The court found the claim for initial damages was discovered in 2006, making it statute-barred by October 2008.
However, the court found a genuine issue for trial regarding continuing nuisance, specifically whether there has been ongoing migration of PHCs from the defendant's property to the plaintiff's property since November 4, 2009, and the extent of resulting damages.
The motion for summary judgment was granted in part, dismissing the initial claim but allowing the continuing nuisance claim to proceed to trial.
Environmental contamination claim dismissed as statute‑barred under discoverability principles.
The defendants brought a motion for summary judgment dismissing an action alleging environmental contamination of the plaintiff’s property by petroleum hydrocarbons migrating from a neighbouring former gas station site.
The defendants argued the claim was statute‑barred under the Limitations Act because it was commenced more than two years after the claim was discoverable.
The court held that the plaintiff knew or ought reasonably to have known of the material facts supporting a claim by March 2012 through environmental investigations conducted during its due diligence period.
The later Phase II environmental report merely confirmed suspicions already known.
The court also rejected the argument that ongoing contamination constituted continuing damage that created a new limitation period due to lack of evidence of fresh damages.
Summary judgment was granted dismissing the action as out of time.