The parties entered into Minutes of Settlement to resolve a dispute over commercial roof repairs and a construction lien.
The settlement required the responding party to rectify specific deficiencies by a deadline, subject to approval by an independent engineering firm, failing which funds held in court would be released to the moving party and the action dismissed.
The engineering firm found the responding party failed to correct all deficiencies.
The moving party sought summary judgment to enforce the settlement, while the responding party cross-moved for relief from forfeiture.
The court granted the moving party's motion and dismissed the cross-motion, finding the settlement terms constituted an agreed-upon forfeiture rather than an unconscionable penalty, and ordered the funds released.