The court dismissed a motion to discharge a construction lien, finding triable issues regarding timeliness and quantum.
The defendant, Hari Kaush Developments Inc. (HKD), brought a motion under sections 47 and 44(5) of the Construction Act to strike the statement of claim, discharge the plaintiffs' claim for lien, and return posted lien security.
HKD argued the lien was untimely and excessive.
The court found triable issues regarding both the timeliness of the lien (due to ambiguity on whether the old or new Construction Act lien period applied and conflicting evidence on the last date of supply) and the quantum of the claim (due to unclear accounting and disputed extras, where oral approval or acquiescence might override written approval requirements).
Consequently, the motion was dismissed in its entirety.
No costs were awarded to either party due to the plaintiffs' egregious delay in complying with undertakings.
The court ordered further documentary discovery, including of settlement documents, and granted partial leave to amend pleadings while awarding costs thrown away for egregious overproduction of irrelevant documents.
The applicants, Gowing Contractors Ltd. and Zurich Insurance Company Ltd., brought a motion seeking further and better production from the defendants Walsh Construction Company Canada and Walsh Construction Co., and leave to amend their pleadings.
The court found that Walsh had overproduced irrelevant documents and failed to produce relevant documents concerning harassment/discrimination allegations and Walsh's delay claim against the City.
The court ordered Walsh to provide a better affidavit of documents, disclose search terms, and produce relevant documents, including those related to its delay claim against the City and its settlement, subject to the City's right to challenge.
Leave to amend pleadings was granted for breach of contract claims but denied for negligence claims and damages related to unrelated projects.
The court also awarded costs thrown away to the applicants due to Walsh's deficient production and late disclosure.
The court validated email service and extended the time for service despite a four-year delay.
Dufferin Communications Inc. brought a motion seeking to validate email service of a statement of claim on one defendant, Paulo A. Almos, extend the time for service, amend the relief claimed to fall within Small Claims Court limits, and transfer the action to the Small Claims Court.
Despite a significant delay of nearly four years in bringing the motion, the court found no prejudice to the defendant, who had been aware of the claim for an extended period.
The motion was granted, validating the service, extending the time, allowing the amendment, and ordering the transfer, with the court also addressing the applicability of the Hague Convention on Service Abroad.
The court awarded full and substantial indemnity costs and pierced the corporate veil against a principal for registering a frivolous construction lien.
This decision concerns the quantum and standard of costs awarded following successful motions by CB Bridle Path Inc. and Jia Development Inc. against 2708320 Ontario Ltd. cob Viceroy Homes.
The motions sought to discharge Viceroy's frivolous and vexatious construction lien and dismiss its action for non-compliance with a prior order.
The court awarded full indemnity costs of $85,000 to Bridle Path and substantial indemnity costs of $45,000 to Jia, finding Viceroy's conduct, including fabricating a lien for extortionary purposes, to be egregious.
The court also pierced the corporate veil to hold Viceroy's principal, Andrew Sun, jointly and severally liable for Jia's costs.
The court awarded reduced partial indemnity costs due to both parties' censurable conduct.
This is a costs and interest decision following a trial where Ben-Air Systems Inc. (plaintiff) was found to have a lien and damages for breach of contract, and the defendants' counterclaim was denied.
Ben-Air sought substantial or partial indemnity costs, while Castlemore Plumbing Limited (defendant) sought costs against Ben-Air and its principal.
The court found Ben-Air to be the successful party overall, recovering 43% of its initial claim.
However, the court criticized the conduct of the principals from both parties, finding them equally censurable.
As a result, neither side was awarded substantial indemnity costs, and no personal liability for costs was imposed on Ben-Air's principal.
Ben-Air was awarded $38,000 in partial indemnity costs, approximately 43% of its partial indemnity claim.
Prejudgment interest was also calculated on two amounts at 0.5% per annum.
A subcontractor's construction lien was vacated because it failed to prove its last date of supply.
This construction lien reference involved a summary trial of an issue concerning the timeliness and bona fide nature of Honeywell Limited's claim for lien against Bondfield Construction Company Limited.
The Lien Vetting Committee, comprising Ozz Electric Inc., Urban Mechanical Contracting Ltd., and Zurich Insurance Company Ltd., argued that Honeywell's lien had expired.
The court found that Honeywell failed to prove its claimed last date of supply, as the evidence provided was deficient and contradictory.
The court also addressed the application of the rule in Browne v. Dunn, concluding it was not engaged because the contradictions were within the witness's own affidavit.
Furthermore, the court commented that even if the last date of supply had been proven, the supply after receiving notice of Bondfield's financial issues would not have been bona fide.
Consequently, Honeywell's lien was ruled to have expired and was ordered vacated.
The court upheld a construction lien for unpaid air conditioning installation, deducting a set-off for incomplete work and a lost warranty.
Novelcare Heating & Cooling brought a claim for lien against Erica Herbert and others for the installation of air conditioning units.
Herbert denied the claim and counterclaimed for damages.
The court found Novelcare breached the contract by failing to complete the work (connecting drains and commissioning units) but did not fundamentally repudiate it.
Herbert failed to prove alleged deficiencies in the installed units.
The court awarded Novelcare the unpaid balance of the contract price, reduced by damages for the incomplete work and a discounted value for the lost warranty, resulting in a lien and damages of $16,085.53 for Novelcare.
A motion for non-party production from a former lawyer was dismissed due to an unresolved lawyer's lien.
The applicant, Carolyn Liddy, brought a motion under Rule 30.10 for production of documents from a non-party lawyer, Jeffrey Streisfield, her former counsel in an underlying negligence action.
The documents sought included files received from previous counsel, work product, and invoices, which were deemed relevant to the current action concerning legal costs incurred to "repair" previous work.
Streisfield asserted a lawyer's lien over the documents due to unpaid accounts.
The court found that Liddy failed to establish that it would be unfair to proceed to trial without the documents, as her inability to obtain them appeared to stem from her unwillingness to pay Streisfield's outstanding account, and she had not brought a necessary motion under Rule 15.03(4) to determine the lien's existence and terms.
The motion for production was dismissed.
Substantial indemnity costs were awarded against a defendant who unnecessarily prolonged a misnomer motion.
This motion was brought by Mappro Realty Inc. seeking to correct a misnomer in the defendant's name from Mizrahi Developments Inc. to Mizrahi Development Group (The One) Inc. While the substantive correction was agreed upon, the court addressed the issue of costs.
The court found that Mizrahi Developments Inc. (MDI) should pay Mappro's costs because MDI knew of the misnomer early on but engaged in conduct, including attempting to preserve a groundless limitation defence, that unnecessarily prolonged the motion and caused Mappro to incur needless costs.
The court awarded Mappro substantial indemnity costs, emphasizing that a misnomer order is an application of law, not an indulgence, and that MDI's conduct warranted sanction.
The court discharged a $3.7 million construction lien as frivolous and dismissed the corporate plaintiff's action.
The defendants, Jia Development Inc. and CB Bridle Path Inc., brought a motion under section 47 of the Construction Act to discharge a construction lien filed by the plaintiff, 2708320 Ontario Ltd. cob Viceroy Homes, and vacate the related certificate of action.
They also sought to dismiss the plaintiff's action due to its failure to appoint new counsel after its previous lawyers withdrew.
The court found the lien claim to be frivolous, vexatious, and an an abuse of process, citing lack of evidence for the claimed work and improper purpose.
Additionally, the plaintiff corporation failed to comply with the order to retain new counsel or obtain leave for non-lawyer representation.
The court granted the defendants' motions, discharging the lien, vacating the certificate of action, and dismissing the plaintiff's action.
The court refused to discharge a construction lien but reduced the conceded posted security.
Trac Developments Inc. ("Trac") moved for an order declaring DNR Restoration Inc.'s ("DNR") construction lien expired due to untimely preservation or, alternatively, reducing the posted security.
The court first determined that the "old" Construction Act applied based on the project's earliest contract date.
Regarding timeliness, the court found genuine issues requiring a trial, as Trac failed to prove DNR abandoned the contract before the lien registration period expired.
On the security reduction, while DNR conceded a significant reduction from its initial claim, Trac's further requested reductions for work orders, May-August work, and rebar accessories were also found to involve triable issues.
Consequently, the motion to declare the lien expired was dismissed, and the security was reduced only to the amount DNR had already conceded plus security for costs.
No costs were awarded due to the mixed success and DNR's initial inflated lien claim.
The court found the contractor wrongfully repudiated the subcontract but denied the subcontractor's unproven claims for extras and delay.
The plaintiff, Ben-Air Systems Inc., brought an action for a construction lien and damages for breach of contract against Castlemore Plumbing Limited and 2664835 Ontario Inc. The claim against 2664835 Ontario Inc. was discontinued.
Ben-Air alleged wrongful repudiation of the subcontract by Castlemore and sought payment for extras and delay costs.
Castlemore counterclaimed for damages to complete the work.
The court found that Castlemore wrongfully repudiated the subcontract, denying its claim for completion costs.
The court denied Ben-Air's claims for specific extras and delay costs due to lack of proof and credibility issues.
The court ultimately determined Ben-Air's lien and damages based on the original contract, undisputed extras, and a judicially determined credit for uncompleted work, dismissing Castlemore's counterclaim.
The court granted the plaintiff an additional 4.5 hours of discovery time but awarded no costs.
The plaintiff brought a motion seeking leave for an additional 7 hours of discovery time for the defendant's representative in a wrongful termination action.
The plaintiff had already conducted 5.5 hours of discovery.
The defendant offered an additional 3 hours, while the plaintiff sought 7.
The court granted the plaintiff an additional 4.5 hours, resulting in a total of 6 additional hours of discovery.
The decision considered the defendant's imprecise pleading, the complexity of the case involving discrimination claims and examination of the defendant's conduct patterns, and the amount at issue.
The court declined to award costs to either party, noting the plaintiff's partial success but also the lack of negotiation efforts for the motion itself.
Motion to dismiss construction lien action for delay denied, but costs awarded against successful plaintiff.
The defendants brought a motion to dismiss the plaintiff's construction lien action for delay under section 47 of the Construction Act and Rule 24.
The action had been delayed for seven years, partly due to an ill-conceived and legally impossible attempt to transfer the lien action to the Small Claims Court.
The court found that despite the plaintiff's egregious delay, a fair trial was still possible as the issues were simple and the defendants' claimed prejudice was unrelated to the delay.
The motion was dismissed, but the court awarded $1,500 in costs to the unsuccessful defendants due to the plaintiff's failure to advance the claim.
A contractor was ordered to pay over $500,000 for wrongfully abandoning a residential construction project.
This case involved a construction dispute where the plaintiff, Save On Contracting, claimed construction liens and damages against the defendant property owners.
The defendants counterclaimed for costs to complete and correct deficiencies, alleging Save On repudiated the contract.
The court analyzed the contract's interpretation regarding Tarion warranty security, whether one of the defendants was a "builder" under the Ontario New Home Warranties Plan Act, and whether Save On fundamentally breached the contract.
The court found that Save On repudiated the contract by making groundless payment demands and abandoning the site.
Consequently, Save On's claims were dismissed, and the defendants were awarded damages for the costs of completing the work and correcting deficiencies.
The court granted default judgment against a contractor and its principal for breach of contract, conversion, and breach of trust, awarding damages based on diminution in value.
Weiyan Li brought motions for default judgment against Guru Constrarchit Ltd. and Guangcheng Zhu (its principal) in two related construction actions, after they failed to engage with the proceedings following removal orders.
The court granted default judgment, finding Guru and Mr. Zhu liable for breach of contract, conversion of project funds, and breach of trust due to significant deficiencies in construction work, misappropriation of funds, and Mr. Zhu's fraudulent conduct and domination of Guru.
Damages were awarded based on diminution in value rather than cost of cure, along with punitive damages and substantial indemnity costs.
Motion to strike pleadings partially granted where defendants pleaded evidence and scandalous allegations.
The plaintiffs brought a motion to strike several paragraphs from the defendants' statement of defence and counterclaim under Rules 25.06(1) and 25.11.
The court struck portions that pleaded evidence rather than material facts, or were scandalous and vexatious.
However, the court retained paragraphs that properly pleaded material facts regarding consent and contributory negligence.
The plaintiffs were awarded costs of $4,500.
Subcontractor's failure to preserve construction lien precludes equitable claims of unjust enrichment against the owner.
The plaintiff subcontractor failed to preserve and perfect a construction lien against the owner's property.
The plaintiff brought a motion for leave to amend its statement of claim to add claims of unjust enrichment and quantum meruit against the owner.
The owner brought a cross-motion to strike the claim against it under Rule 21.
The court dismissed the plaintiff's motion and granted the owner's motion to strike, holding that the Construction Act is a complete code and a subcontractor who fails to preserve its lien rights has no equitable recourse against the owner.
Costs awarded to moving party after responding parties provided statutory information late, necessitating a motion.
The moving party brought a motion to compel the responding parties to provide information required under section 39 of the Construction Act.
The responding parties provided the requested information after the motion was served but before the hearing.
The moving party sought costs of the motion.
The court awarded costs to the moving party, finding that the responding parties caused the unnecessary motion by failing to respond to the section 39 demand within the statutory 21-day period and making no reasonable effort to resolve the motion costs.
Motion to dismiss for delay denied as plaintiff adequately explained delay caused by former counsel's murder.
The defendant brought a motion to dismiss the plaintiff's breach of contract action for delay under Rules 48.14(7)(a) and 24.01.
The court found that the plaintiff adequately explained the delay, which was largely due to the health issues and subsequent murder of the plaintiff's former counsel, as well as concurrent delays by the defendant.
The court also found no significant prejudice to the defendant.
The motion was dismissed, a new litigation schedule was imposed, and costs of $25,000 were awarded to the plaintiff.