The plaintiff contractor brought a construction lien action for unpaid invoices and extras related to a balcony repair project.
The defendant owner counterclaimed for delay costs and defective workmanship, including undersized balconies and damaged railings.
The court dismissed both parties' delay claims due to a lack of expert evidence and failure to comply with contractual notice provisions.
The court awarded the plaintiff its unpaid invoice, holdback interest, and extras for slab replacement, while granting the defendant partial backcharges for the undersized balconies and damaged railings.
Ultimately, the plaintiff was awarded a net judgment of $44,999.19 and a valid lien.