A construction lien dispute arising from the termination of a mechanical subcontract.
The plaintiff, a mechanical contractor, claimed a lien for unpaid work and damages for wrongful termination.
The defendant, the construction manager, terminated the subcontract citing multiple defaults including failure to provide adequate manpower, delays in completing critical work, and failure to correct deficiencies.
The court found the defendant properly exercised its contractual right to terminate based on the plaintiff's failure to properly and diligently perform the work, but awarded the plaintiff the net unpaid balance of the subcontract after deducting the defendant's completion costs and other back-charges.