The plaintiff, New Generation Woodworking Corp. (NGW), brought a construction lien action against Adam Arviv for $73,767.26 for unpaid millwork on a luxury condominium unit.
Arviv defended and counterclaimed for alleged overpayment and deficiencies, but his counterclaim was struck due to his persistent non-compliance with court orders and lack of engagement.
The court found that Arviv had repudiated the contract by ceasing payments and denying access, and that NGW had substantially completed its work.
The court ruled in favour of NGW, awarding the full amount claimed and confirming the validity and priority of its construction lien over Arviv's property and a second mortgage, with limited priority over the first mortgage to the extent of the basic holdback deficiency.