The plaintiff paving contractor sued the defendant general contractor for unpaid invoices and extras on a construction project (the Archmill project).
The plaintiff had also refused to perform work on a second, unrelated project (the Burgessville project) until it was paid for the first.
The court found that the plaintiff was entitled to payment for some, but not all, of the disputed extras on the first project.
However, the court also held that the plaintiff's refusal to work on the second project constituted an anticipatory breach of contract.
The defendant was awarded damages for the extra costs incurred to complete the second project, and the court allowed the defendant to equitably set off those damages against the amount owed to the plaintiff on the first project.
The plaintiff's claim for breach of trust under the Construction Act was dismissed.