This appeal and cross-appeal arose from a failed residential subdivision development project in Fort Erie, Ontario.
The central issues were whether the parties had entered into an enforceable written agreement dated December 13, 2005, whether there was a breach or repudiation of that agreement, and the validity of a construction lien filed by Ravenda Homes.
The motion judge had dismissed Ravenda Homes's breach of contract action, vacated its certificate of pending litigation, allowed its lien action, and allowed the respondent's counterclaim in part.
On appeal, the Court of Appeal upheld most of the motion judge's findings but set aside the award of damages under section 35 of the Construction Lien Act, referring that issue to trial.