The defendant municipality brought a motion for summary judgment dismissing a contractor’s claim arising from a tender competition for construction of a medical centre.
The contractor alleged that the municipality breached Contract A by failing to award the project to it after applying an alternate price credit related to winter suspension of construction.
The court found that construction did not begin in fall 2013 and was never suspended during the winter as alleged in the pleadings, rendering the alternate credit inapplicable.
The municipality was entitled to evaluate bids based on base bid prices and was not required to adjust bids using alternate credits that were irrelevant to the project as ultimately undertaken.
Summary judgment was granted and the action dismissed.