Drainage appeal dismissed and engineer's report affirmed, but engineering costs capped due to excessive delay.
The appellants appealed the final engineer's report for the proposed Frank Szeder Drain under section 48 of the Drainage Act, arguing that the project was delayed excessively and the proposed design was flawed and too costly.
The Tribunal found that while the 12-year delay was excessive, the appellants failed to provide evidence that the proposed drainage work was technically flawed or that the costs outweighed the benefits.
The Tribunal dismissed the appeal and affirmed the engineer's report, but limited the chargeable engineering costs to $108,130 to account for the excessive delay.
Frank Szeder Jr. and the Szeder Estate v. Township of Emo and Township of La Vallee, 2025 ONAFRAAT 11