The plaintiff demolition subcontractor brought a lien action for unpaid work, and the defendant general contractor counterclaimed for damages caused when the plaintiff severed an underground electrical duct bank, causing a power outage at a wastewater treatment plant.
The court found the plaintiff breached its subcontract and was negligent by failing to review drawings, obtain locates, and follow its own demolition plan.
However, the court also found the defendant 15% contributorily negligent for failing to communicate its knowledge of the duct bank to the plaintiff.
The plaintiff's lien claim was offset against 85% of the defendant's damages, resulting in a net judgment payable by the plaintiff to the defendant.