10 total
The court dismissed the plaintiff's construction action for inordinate and inexcusable delay under Rule 24.01.
The defendants, McDonald Brothers Construction Inc. et al., brought a motion to dismiss the plaintiff's claim for delay under Rule 24.01 of the Rules of Civil Procedure.
The action, commenced in 2016, had seen no progress since discoveries in 2018, and the plaintiff failed to comply with a 2019 order to retain new counsel.
The court found the delay to be inordinate and inexcusable, rejecting the plaintiff's explanations related to personal health, financial difficulties, and the pandemic.
Despite no finding of intentional or contumelious conduct, the plaintiff failed to rebut the presumption of prejudice arising from the delay.
The motion was granted, and the action was dismissed with costs awarded to the defendants.
The court granted summary judgment enforcing a settlement agreement for unpaid construction invoices, rejecting defenses of duress and mistake.
This was a motion for summary judgment to enforce a settlement agreement.
The respondents argued the agreement should be set aside due to duress, misrepresentation, and mistake of fact, contending a full hearing was required.
The court found the matter suitable for summary judgment under Rule 20 and Hryniak v. Mauldin.
The court dismissed the respondents' arguments, finding insufficient evidence for duress, no fundamental mistake regarding the agreement's terms (including CPP, EI, and taxes), and no basis for negligent misrepresentation.
Summary judgment was granted to the moving party, enforcing the settlement agreement, and substantial indemnity costs were awarded against the respondents.
The court adjourned a consent motion to amend pleadings due to numerous procedural and filing deficiencies.
The plaintiff brought a motion for leave to amend the statement of claim, seeking to add a new defendant and remove an existing one.
The court identified numerous procedural deficiencies in the motion record, including an improper basis for bringing the motion in writing (expectation of unopposed vs. consent), lack of affidavit of service for the proposed new party, use of antiquated terminology ("style of cause"), and issues with the consent form and document filing.
The motion was not granted at this time and was adjourned with specific directions for the plaintiff to correct the record and ensure proper service on all parties, including the proposed new defendant.
The court awarded partial indemnity costs to the contractors after they successfully defended a motion to strike their construction liens.
This decision addresses the costs of a previously dismissed motion brought by 256613 Ontario Inc. (the Owner) to strike and discharge construction liens registered by GTA General Contractors Ltd. and Karar Al-Najari (the Contractors).
The Contractors, having successfully defended the Owner's motion, sought costs on a substantial indemnity scale.
The court, considering the complexity and importance of the liens but noting the Contractors' unsuccessful argument regarding the interlocutory nature of the Owner's motion, awarded costs on a partial indemnity scale in the amount of $6,700, including HST and disbursements.
Appeal allowed; second construction lien discharged as s. 48 of the Construction Lien Act makes discharge of first lien irrevocable.
The appellant general contractor appealed a motion judge's refusal to discharge a second construction lien registered by the respondent subcontractor.
The respondent had registered a first lien, discharged it due to an error in the dates of service, and registered a second lien for the same amount.
The Divisional Court allowed the appeal, finding that under s. 48 of the Construction Lien Act, the discharge of a lien is irrevocable and the lien cannot be revived.
The motion judge erred in finding the first lien a nullity without giving the parties an opportunity to make submissions, and in failing to consider the curative provision in s. 6 of the Act.
The second lien was ordered discharged.
Summary judgment granted dismissing third party claim as it was barred by a prior global settlement agreement.
The Third Party, a municipality, brought a motion for summary judgment to dismiss a Third Party Claim brought by the Defendant general contractor.
The claim arose from a municipal infrastructure project where a provisional item was deleted from the contract.
The parties had previously entered into a Global Settlement Agreement to resolve all outstanding claims.
The court found that the summary judgment process was appropriate as there were no credibility issues requiring a trial.
The court interpreted the Global Settlement Agreement and concluded that the specific claim was subsumed within the settlement, barring the Defendant from asserting further claims.
The motion for summary judgment was granted.
Appeal allowed; Divisional Court erred by voiding contract based on unpleaded doctrine of common mistake.
The respondent contractor hired the appellant for epoxy flooring based on a sketch with inaccurate elevations.
When the appellant discovered the error and sought a price increase, the respondent refused, leading to a breach of contract claim and a counterclaim for lost profits.
The trial judge found for the appellant, but the Divisional Court overturned the decision on its own initiative, applying the doctrine of common mistake.
The Court of Appeal allowed the appeal, holding that the Divisional Court erred by deciding the case on unpleaded grounds and misapplying the doctrine of common mistake, as the mistake was the respondent's fault.
Motion for a stay of building orders denied; public interest in heritage preservation outweighs financial harm.
The applicants sought a stay of orders issued by the respondent municipality under the Building Code Act regarding their heritage buildings, which were in an unsafe condition.
The applicants wanted to demolish the buildings without complying with the heritage permit conditions.
The court applied the RJR-Macdonald test and dismissed the motion for a stay, finding no serious issue to be tried, no irreparable harm, and that the balance of convenience favoured the public interest in preserving heritage buildings and ensuring safety.
Action for unpaid masonry work and counterclaim for defects both dismissed due to shared responsibility.
The plaintiff masonry company brought an action for unpaid services under a verbal, cash-based contract for the installation of stone veneer and chimneys on the defendants' new home.
The defendants counterclaimed for the cost of remedial work, alleging the masonry was defective and not compliant with the building code.
The court found that both parties entered into an imprecise, 'under the table' arrangement and shared responsibility for the project's shortcomings.
Concluding that the plaintiff received less than expected but was entitled to less due to the final result, and that the defendants as builder/contractors bore responsibility for the conditions, the court dismissed both the main action and the counterclaim.
Fundamental mistake in construction tender documents rendered the contract void, precluding damages for either party.
The appellant general contractor sued the respondent subcontractor for breach of contract after the respondent refused to commence work without an agreement for extra costs due to inaccurate tender documents.
The respondent counterclaimed for loss of profit and surveying costs.
The trial judge dismissed the appellant's claim and awarded damages to the respondent.
On appeal, the Divisional Court found that the substantial errors in the tender documents constituted a fundamental mistake that rendered the contract void.
Consequently, neither party was entitled to damages.
The appeal was allowed in part, setting aside the trial judgment in favour of the respondent.