Wessuc Inc. sued Todd Brothers Contracting Limited and The Guarantee Company of North America (GCNA) for breach of contract, unjust enrichment, and breach of trust related to a sludge removal contract.
Todd counterclaimed for Wessuc's failure to complete the contract.
The court found that the contract was a lump sum agreement for 6100 m³ of sludge removal, not a per-unit price for total volume including water.
Wessuc abandoned the project by ceasing work and failing to provide a plan for completion, entitling Todd to terminate the contract.
Wessuc's claim for damages and quantum meruit was dismissed as it did not substantially complete the work.
Todd's counterclaim for costs incurred to complete Wessuc's work, including cattail removal, equipment, fuel spill cleanup, and sand/sawdust for drying sludge, was allowed for $53,000.
GCNA was found to have no obligations under the bond due to Wessuc's failure to provide timely and adequate notice.