The plaintiffs, developers of two condominium buildings, sought an extension of time to serve statements of claim against the respective condominium corporations for unpaid promissory notes related to guest suites.
The statements of claim were issued in March 2020 but not served until July 2022, past the extended deadline of March 2021.
The delay was attributed to counsel's inadvertence.
The defendants opposed, arguing abandonment and prejudice due to witness unavailability and changes in unit ownership.
The court, applying the principles from Chiarelli v Wiens, found that the plaintiffs intended to pursue the actions and that the delay was due to inadvertence.
The court rejected the defendants' claims of prejudice, noting their early notice of the claims and that any alleged prejudice was not caused by the delay or was speculative.
The motions for extension of time were granted.