The plaintiffs, two lienholders, brought a motion opposing the confirmation of a Master's Report which found that the defendant mortgagees had priority over their construction liens under s. 78(3) of the Construction Act.
The Master had awarded the mortgagees all proceeds from the receivership sale of the contaminated property.
The Superior Court confirmed the Master's finding that the mortgagees had priority for the funds advanced under the vendor take-back mortgage.
However, the Court set aside the portion of the Report granting the mortgagees priority for additional fees, charges, and expenses not directly related to the sale, allowing the lienholders access to the remaining funds to satisfy their liens.