The applicant appealed the City of Toronto's failure to adopt a requested Official Plan Amendment to redevelop the Richard L. Hearn Generating Station into a mixed-use neighbourhood.
At a Case Management Conference, the Toronto Port Authority, Ministry of Municipal Affairs and Housing, GFL Environmental Inc., Amrize Canada Inc., and Portlands Energy Centre L.P. sought and were granted party status on consent.
A second Case Management Conference was scheduled to allow the parties to finalize a draft Procedural Order and issues list.