Dirm 2010 Inc. brought a construction lien claim against Prestressed Systems Incorporated (PSI) for unpaid work on a concrete topping subcontract for a parking garage.
PSI counterclaimed, alleging Dirm's work was defective and that Dirm fundamentally breached the contract.
The court found that the contract consisted of the negotiated terms, not the onerous unsigned purchase order PSI attempted to impose.
The court held that Dirm's work, while requiring some remediation, did not constitute a fundamental breach.
PSI breached the contract by terminating Dirm without reasonable opportunity to cure and without justification.
Dirm was awarded $1,315,159.20 for completed work, allowable extras, and lost profit, less reasonable backcharges for deficiencies.