The plaintiff demolition contractor registered a construction lien after abandoning the site due to the defendant developer's failure to pay a progress draw.
The dispute centered on whether the contract required crushing concrete to 3-inch minus or 3/4-inch minus, and whether the plaintiff was responsible for removing asphalt and imported materials.
The court found the defendant breached the contract by failing to pay the progress draw, the contract specified a 3-inch minus crush, and the lien was registered in time.
After accounting for payments and proven backcharges, the defendant was ordered to pay the plaintiff $81,271.93.