The plaintiff contractor sued the defendant owner for approximately $17,000 in unpaid services related to a house renovation project.
The defendant counterclaimed for approximately $90,000, alleging overcharging, incomplete work, and defective construction, including a deviation from the cathedral ceiling design.
The court found that the plaintiff had completed over 90% of the contracted work and was entitled to payment for work performed and agreed extras.
The court rejected the defendant's claim of fundamental breach, finding the ceiling deviation immaterial, but awarded the defendant minor damages for delay and minor deviations.
The plaintiff was awarded a net sum of $15,960.37.