The appellant purchased a former waste disposal site and inherited an Environmental Compliance Approval requiring post-closure monitoring and financial assurance.
The Director issued an order requiring the appellant to submit financial assurance of $74,638.
The appellant appealed, arguing they should not have to pay until a civil suit against the prior owner was resolved.
The Ontario Land Tribunal dismissed the appeal, finding the appellant had not complied with monitoring requirements and that delaying the financial assurance was not in the public interest.
The Tribunal confirmed the Director's order and set a payment deadline of May 1, 2026.