The appellants appealed a cost recovery order issued by the Director of the Ministry of the Environment, Conservation and Parks following an explosion and fire at a hazardous waste processing facility.
Prior to the hearing, the parties reached a proposed settlement reducing the payable amount from $133,097.14 to $100,000, removing the individual directors from the order, and requiring a site closure plan.
The City of St. Catharines sought Party status but was granted Participant status to make oral submissions.
The Tribunal found the proposed settlement consistent with the Environmental Protection Act and in the public interest, as it ensured recovery of reasonable costs and provided for the prompt closure and remediation of the site.
The appeal was allowed in part to implement the settlement.