The respondent, a flooring contractor, was hired by the appellant general contractor to install sheet vinyl flooring at a long-term care facility.
When the respondent identified deficiencies in the sub-floor structure that prevented proper installation, the appellant refused to remedy the defects and instead directed the respondent to attempt a temporary fix.
After the temporary fix failed and the project architect required the flooring to be removed and replaced, the respondent refused to continue without payment for previous work and relief from warranty obligations.
The appellant hired another contractor to complete the work and counterclaimed for abandonment.
The trial judge found the respondent unable to perform due to sub-floor defects that were the appellant's responsibility to remedy, awarded damages for breach of contract, and dismissed the counterclaim.
The appellant appealed, and the respondent cross-appealed on damages assessment.