The defendant Aizenstros brought a motion seeking a declaration that the plaintiff Nigeco's construction lien was invalid, arguing it was registered out of time because the contract was either terminated by Aizenstros on June 13, 2017, or abandoned by Nigeco on June 5, 2017.
Nigeco contended the contract was never completed and the lien was validly registered within 45 days of Aizenstros abandoning it.
The court found that the contract was neither abandoned by Nigeco nor terminated by Aizenstros on the dates claimed, as post-purported termination conduct, including a site visit and continued negotiations, indicated an ongoing intention to complete the project.
The court determined the contract was terminated by Nigeco on August 3, 2017, when Aizenstros failed to respond to resolution efforts.
Consequently, the lien was valid, and the defendant's motion was dismissed.