6 total
Appeal dismissed; renewable energy contract automatically terminated upon bankruptcy without violating the anti-deprivation rule.
The appellant, a secured creditor of a bankrupt renewable energy company, appealed the dismissal of its action against the Independent Electricity System Operator (IESO).
The appellant argued that the IESO wrongfully treated a renewable energy contract as terminated upon the debtor's bankruptcy, thwarting the appellant's attempt to assign the contract to a third party.
The Court of Appeal dismissed the appeal, affirming that the contract automatically terminated upon bankruptcy, that this termination did not violate the Bankruptcy and Insolvency Act stay of proceedings or the common law anti-deprivation rule, and that the IESO did not breach its contractual obligations or act negligently.
Motion for leave to appeal dismissed with costs fixed at $5,000.
The appellants brought a motion for leave to appeal the decision of Corthorn J. dated November 4, 2019.
The Divisional Court dismissed the motion for leave to appeal and awarded costs to the responding parties fixed at $5,000 inclusive.
Motion granted decision
The plaintiff sought costs after successfully opposing the defendants' motion to set aside or discharge a certificate of pending litigation.
The court had previously found that the plaintiff failed to make full and frank disclosure on the original ex parte motion for the certificate, but that the certificate would have been granted anyway.
The defendants argued against costs due to the disclosure failure.
The court reserved costs of the motion to the trial judge, citing divided success on the motion (plaintiff won on substantive issue, defendants won on disclosure finding), the reasonableness of the defendants' motion, the early stage of the action, and the potential for litigation conduct to be a factor at trial.
Action for breach of renewable energy contract dismissed as bankruptcy triggered automatic termination clause.
The plaintiff sought damages of approximately $4.8 million for breach of contract, negligent misrepresentation, and breach of the duty of good faith arising from a renewable energy contract.
The plaintiff acquired the secured debt of a company that had a contract with the defendant to build a biomass energy facility.
When the company filed for bankruptcy, the defendant treated the contract as automatically terminated pursuant to its terms, requiring the plaintiff to seek a new agreement.
The court dismissed the action, finding that the contract unambiguously provided for automatic termination upon bankruptcy, the defendant did not act in bad faith, and the plaintiff failed to mitigate its damages and prove an enforceable agreement for the sale of the contract.
Joint trial jurisdiction confirmed; appeal dismissed despite dissent on legislative intent.
The Court dismissed the appeal and held that an Ontario Court of Justice judge had jurisdiction to conduct a joint trial of provincial offences and summary conviction criminal offences arising from the same events.
The majority applied a functional joinder approach and found a sufficient factual nexus, no statutory prohibition, and no prejudice.
A dissent would have found no jurisdiction based on legislative intent behind the Provincial Offences Act and would have ordered new trials.
Costs of successful interim motion fixed at $23,810.59 on a partial indemnity basis.
The applicants were successful on an interim motion permitting the individual applicant to resume his day-to-day involvement in the parties' businesses.
The court was asked to determine the costs of the motion.
The respondents argued costs should be in the cause, while the applicants sought substantial indemnity costs payable immediately.
The court found that the respondent's conduct in unilaterally ousting the applicant without colour of right justified an order of costs in any event of the cause.
However, the court awarded costs on a partial indemnity basis, fixing them at $23,810.59 inclusive of fees, disbursements, and HST.