The plaintiff subcontractor sued the defendant general contractor for unpaid invoices and extra work performed on a municipal renovation project.
The defendant refused to pay, alleging the plaintiff mismanaged the project, caused significant delays, and performed deficient work, and brought a counterclaim for costs to complete and rectify the work.
The court found the defendant's principal witness lacked credibility and that the defendant had orally approved the extra work, establishing a quantum meruit claim.
The court dismissed the counterclaim, finding no evidence of deficient work and noting the defendant failed to provide contractual notices of default.
The plaintiff was awarded $188,514.62 and its construction lien was declared valid.