The plaintiff landscaping company brought a construction lien action for an unpaid balance of $19,465.00 for stonework performed at the owner's property.
The defendants counterclaimed for damages for delay and deficiencies.
At the reference, the plaintiff moved to strike portions of a defendant's affidavit that contradicted an admission made on discovery that the defendant had not corrected the alleged deficiencies.
The court refused to allow the withdrawal of the admission, finding it would cause non-compensable prejudice.
The court granted the plaintiff's claim, finding the delays were caused by the general contractor and there was no evidence of deficiencies.
The general contractor was ordered to pay the outstanding balance, and the owner was found personally liable for the $18,000.00 statutory holdback.
The counterclaim was dismissed.