The plaintiff framing contractor brought three construction lien actions against the defendants arising from a joint venture to purchase, sever, and redevelop residential lots.
The court found that the plaintiff was not an 'owner' under the Construction Lien Act and was owed $70,400 for its contract scope of work plus $21,824.43 for conceded extras.
However, the court dismissed the plaintiff's claims for site supervision and other extras, finding they were part of the plaintiff's principal's obligations to the joint venture.
The court also held that the plaintiff's lien rights had expired before registration, as the work allegedly done within the 45-day period was not performed by the plaintiff.
The claims for lien were discharged and judgment was granted for breach of contract.