The applicant sought an order under s. 6 of the Arbitration Act, 1991 referring a contractual dispute to arbitration under a specific multi‑party arbitration procedure contained in a power supply contract.
The respondent agreed the dispute should proceed to arbitration but argued that a different contractual arbitration clause governed, requiring a single arbitrator to determine issues of contractual interpretation before any broader arbitration process could be triggered.
The court interpreted the contract as containing both a universal arbitration clause for general disputes and a limited clause applicable only if certain economic conditions were established.
The court held the dispute concerned interpretation of the agreement and therefore fell within the general arbitration clause.
The motion was dismissed and the matter directed to proceed before a sole arbitrator.