8 total
Motion for leave for judicial review of adjudicator's decision dismissed with costs.
The moving party brought a motion for leave for judicial review of an adjudicator's decision.
The Divisional Court dismissed the motion for leave and awarded costs to the responding party in the fixed amount of $2,907.60.
Motion for leave to appeal dismissed with no costs awarded.
The moving party sought leave to appeal a prior decision of the Superior Court of Justice.
The Divisional Court dismissed the motion for leave to appeal.
As no costs outlines were filed, the court ordered that no costs be awarded.
A surety's registered security interest under an indemnity agreement takes priority over a subcontractor's interim adjudication award under the Construction Act.
A surety (Westport) brought an interpleader motion seeking a declaration of priority over funds awarded to a subcontractor (High Tech) in an ODACC adjudication, or alternatively, for the funds to be paid into court.
The funds were held in trust by the general contractor's (BDA) counsel due to competing claims.
The court found that Westport, as surety, had a valid security interest and trust claim over the funds based on the indemnity agreement with High Tech.
The court rejected High Tech's argument that the Construction Act's prompt payment provisions gave it priority.
However, the court also found that there were triable issues regarding Westport's good faith in processing claims and making advances, which precluded a final order for immediate payment to Westport.
Therefore, the court ordered the disputed funds to be paid into court pending the outcome of ongoing litigation between the parties.
Funds held in a lawyer's trust account do not constitute payment to a lien claimant.
The defendant, BDA Inc., brought a motion to reduce the bond filed as security in a construction lien matter, arguing that funds paid to its lawyers in trust, pursuant to an ODACC adjudication determination, should be credited against the lien amount.
The plaintiff, High Tech Power Inc., opposed the full reduction, contending that funds held in trust by the defendant's counsel were not "paid" to the lien claimant and thus could not stand as security.
The court ruled that funds held in a lawyer's trust account on behalf of the client do not constitute payment to the lien claimant and cannot be considered security for the lien, as they do not ensure the flow of money as intended by the Construction Act.
The motion for a full reduction was dismissed, and the bond was reduced only by the amount High Tech Power Inc. had consented to.
Motion for leave to appeal dismissed with no order as to costs.
The moving parties sought leave to appeal an order of Emery J. The Divisional Court dismissed the motion for leave to appeal.
The court made no order as to costs because the responding party failed to provide a costs outline.
Divisional Court establishes test for leave to judicially review Construction Act adjudicator decisions.
The moving party sought leave to apply for judicial review of an adjudicator's decision under the prompt payment provisions of the Construction Act.
The Divisional Court established the test for granting leave in such cases, noting that adjudicators' decisions are interim and leave should rarely be granted.
The court held that the test is analogous to the conjunctive test for leave to appeal an interlocutory order.
Finding that the moving party did not meet this high bar, the court dismissed the motion for leave with costs.
Judicial review application dismissed because the applicant failed to pay the adjudicator's order or obtain a stay.
The applicant sought judicial review of an adjudicator's decision under the prompt payment provisions of the Construction Act.
The applicant had neither paid the amount ordered by the adjudicator nor obtained a stay of the decision pending the application.
The Divisional Court dismissed the application, holding that failure to comply with a prompt payment order without a stay undercuts the statutory scheme, and invoked equity to decline to hear the application on its merits.
A punitive damages award was set aside because the motion judge provided no analysis.
The Court of Appeal for Ontario allowed an appeal concerning an award of punitive damages.
The motion judge had awarded $50,000 in punitive damages without providing any analysis or reasons for the award.
The appellate court found that this lack of analysis rendered the decision unreviewable, concluding that punitive damages are an exceptional remedy requiring proper justification.
Consequently, the appeal was allowed, and the punitive damages award was set aside.