This decision addresses motions in three consolidated construction lien actions.
Sutton Forming Inc. sought a declaration on Homes by DeSantis (Lake) Inc.'s minimum holdback obligation under the Construction Lien Act and an order for payment from it.
The court clarified that the holdback is calculated based on the contract price for services actually supplied, not amounts paid, and rejected the owner's objections regarding certificate accuracy and set-off for deficiencies.
The court granted leave for the motion, declared the minimum holdback, and ordered specific payments to Sutton and its sub-subcontractors from the holdback.