4 total
Post-bankruptcy costs award cannot be set off against creditor’s proven bankruptcy claim.
A creditor in a bankruptcy proceeding sought a declaration permitting set-off of a substantial costs award owed to the bankrupt against the creditor’s proven unsecured claim in the bankruptcy estate.
The court considered whether the claim satisfied the requirements for legal or equitable set-off under the Bankruptcy and Insolvency Act.
It held that legal set-off was unavailable because the costs debt arose after the bankruptcy and lacked the necessary mutuality with the creditor’s claim against the estate.
Equitable set-off was also unavailable because the adverse costs award related to a discrete tort claim and was not sufficiently connected to the contractual debt forming the creditor’s proven claim.
The motion for set-off was dismissed, and the court granted the bankrupt’s counsel a charging order over the costs award pursuant to the Solicitors Act, giving the solicitor priority as a secured creditor.
Creditor authorized to pursue recovery action under Bankruptcy and Insolvency Act s. 38.
A bankrupt sought a discharge under s. 169 of the Bankruptcy and Insolvency Act.
Two creditors opposed the discharge and requested authorization under s. 38 of the Act to pursue recovery proceedings in the trustee’s name where the trustee declined due to lack of funds.
The court reviewed the complex financial history of the bankrupt, including transfers of real property, potential settlements within five years of bankruptcy, and substantial payments relating to the bankrupt’s spouse’s medical care.
The court concluded that a creditor‑initiated s. 38 proceeding could provide the only realistic opportunity for recovery for the estate and imposed conditions for creditor notice, participation, and court approval of any settlement.
The discharge hearing was adjourned pending further developments.
Appeal and cross-appeal of construction lien trial judgment dismissed as no palpable error found.
The appellant homeowner appealed a trial judgment awarding the respondent contractor damages for unpaid holdbacks and construction extras, while the contractor cross-appealed the partial allowance of the homeowner's counterclaim for deficiencies and delay.
The Divisional Court dismissed both the appeal and cross-appeal, finding that the trial judge made no palpable and overriding error in her assessment of the conflicting evidence regarding the construction of the new home, including the parties' failure to strictly follow the contractual procedure for requesting extras.
Appeal dismissed without costs on consent of the parties.
The appellants appealed an order of the Superior Court of Justice.
On consent of both parties, the Court of Appeal dismissed the appeal without costs.