The defendants applied under Rule 54.09(2) to oppose confirmation of a master's report following a 12‑day construction lien trial.
The master had found that the owner repudiated the construction contract, that performance milestones were implicitly amended due to design and structural changes imposed by the owner, and that the contractor was entitled to damages and a construction lien.
On review, the court applied the appellate standard of review requiring an error in principle or palpable and overriding error.
The court held that the master's factual findings regarding the applicable construction plans, scope changes, and amended milestone sequence were supported by the evidence and entitled to deference.
The application to oppose confirmation of the master's report was dismissed.