The defendants brought a Rule 21 motion to determine questions of law regarding applicable limitation periods and proper parties in an action for damages arising from a municipal drain.
The court held that the limitation period in s. 111 of the Drainage Act applies only to proceedings before a referee, not the Superior Court, meaning s. 45 of the former Limitations Act applied to the plaintiffs' claims.
The court also found that the one-year limitation period under s. 46 of the Professional Engineers Act applied to the claims against the engineering defendants.
Finally, the court determined that under s. 79 of the Drainage Act, the municipality is strictly liable for damages caused by the condition of drainage works, precluding claims against the other defendants.