The moving party brought a motion for an extension of time to file an application for judicial review of an Ontario Land Tribunal decision regarding a developer's site plan application.
The Tribunal had found the application complete despite the developer failing to attend a mandatory pre-application consultation.
The court granted the extension, finding the moving party's delay was short and adequately explained by its initial attempt to seek leave to appeal, and that the proposed application raised apparent grounds for relief that should be determined by a panel.