The Receiver sought and obtained two orders: a Construction Continuance Order to approve the engagement of a new construction manager (SKYGRiD) and extend a stay of proceedings, and a Lien Regularization Order to establish a court-supervised process for construction lien claims.
The court found jurisdiction under the Bankruptcy and Insolvency Act and the Courts of Justice Act, concluding that the orders were necessary and appropriate to ensure the ongoing construction of "The One" project and to manage lien claims efficiently without prejudicing claimants' substantive rights.
Objections from the former developer (Mizrahi Parties) regarding their own pending motion for fees were acknowledged but did not prevent the approval of the Receiver's requested orders.